My watchlist
Updating…
Data
Checking the feed…
You
My watchlist
Display
Estimates are derived by T2C from disclosed figures. Switch them off to see only what companies have published.
Focus mode Supporting context hidden. Figures, their basis, confidence and sources are unchanged — nothing that qualifies a number is hidden.

Research

The full evidence base: every figure, every source, every correction. Start with the summary and open only what you need.

Research summary

Where the data stands today
Secured power
≥15.5 GW
5 of 6 companies, gross-utility basis
Customers have signed for
≥2.51 GW
3 disclose on a critical-IT basis; 3 do not
Switched on
≥1.75 GW
4 disclose energised critical IT
Delivered and accepted
50 MW
1 company discloses formal acceptance
Guided milestones
10
1 reached and scoreable, 9 outstanding

Contributor sets differ between rows. These are not stages of one funnel.

Explore the data Capacity records, ledger, contracts and sources

Capacity explorer

Every value with its evidence
Scroll sideways for all columns →
CompanyModel Secured powerCustomer-contractedEnergised critical ITCustomer-acceptedRevenue live Last verified
IRENIREN Limited Full stack 5 GW ConfirmedGross ↗ sec.gov ↗ sec.govas of 31 Mar 2026≥260 MW ConfirmedDisclosed minimumCritical IT ↗ sec.gov ↗ sec.govas of 1 Jun 2026≥50 MW ConfirmedDisclosed minimumCritical IT ↗ globenewswire.comas of 13 Aug 202650 MW ConfirmedCritical IT ↗ globenewswire.comas of 13 Aug 2026Not disclosed Not disclosed 15 Aug 2026
CRWVCoreWeave Full stack 4.20 GW ConfirmedGross ↗ investors.coreweave.comas of 11 Aug 2026Not disclosed Not disclosed 1.50 GW ConfirmedCritical IT ↗ investors.coreweave.comas of 30 Jun 2026Not disclosed Not disclosed Not disclosed Not disclosed 15 Aug 2026
NBISNebius Group Full stack ≥3.50 GW ConfirmedDisclosed minimumGross ↗ sec.govas of 31 Mar 2026Not disclosed Not disclosed Not disclosed Not disclosed Not disclosed Not disclosed Not disclosed Not disclosed 15 Aug 2026
WULFTeraWulf Powered shell Not disclosed Not disclosed ≥839 MW ConfirmedDisclosed minimumCritical IT ↗ investors.terawulf.com ↗ investors.terawulf.comas of 4 Aug 2026102 MW ConfirmedCritical IT ↗ investors.terawulf.comas of 30 Jun 2026Not disclosed Not disclosed 102 MW ConfirmedCritical IT ↗ investors.terawulf.comas of 30 Jun 2026 15 Aug 2026
KEELKeel Infrastructure Powered shell 648 MW ConfirmedGross ↗ sec.govas of 31 Mar 2026No announced leaseNot disclosed Not disclosed Not disclosed Not disclosed Not disclosed Not disclosed 15 Aug 2026
APLDApplied Digital Powered shell 2.15 GW ConfirmedGross ↗ sec.govas of 31 May 20261.41 GW ConfirmedCritical IT ↗ sec.govas of 31 May 2026100 MW ConfirmedCritical IT ↗ sec.govas of 31 May 2026Not disclosed Not disclosed 100 MW ConfirmedCritical IT ↗ sec.govas of 31 May 2026 15 Aug 2026

Delivery ledger

16 verified events
16 events
13 Aug 2026 announced 13 Aug 2026

IREN Limited — Horizon 1 — 50 MW of critical IT — delivered to and accepted by Microsoft.

The only formally accepted hyperscaler capacity across every company tracked here. Acceptance is the milestone that normally starts the revenue clock, but IREN has not separately disclosed that billing has commenced, so it is not recorded as revenue-live.

Confirmed high significance customer accepted ↗ globenewswire.com
Not disclosed 50 MW
11 Aug 2026 announced 11 Aug 2026

CoreWeave — Contracted power reached approximately 4.2 GW, up from 3.7 GW at quarter end.

A further 500 MW of supply secured within six weeks of the quarter close. Contracted power is a total that already includes active capacity, so this widens the gap between power controlled and power energised rather than closing it.

Confirmed high significance capacity change ↗ investors.coreweave.com ↗ investors.coreweave.com
3.70 GW 4.20 GW
30 Jun 2026 announced 11 Aug 2026

CoreWeave — Active power expanded by nearly 500 MW to reach 1.5 GW.

The largest single-quarter energisation step on the board. The previous value is derived from the company's own "expanded by nearly 500 MWs" wording rather than a separately published Q1 figure.

Confirmed high significance capacity change ↗ investors.coreweave.com
1 GW 1.50 GW
30 Jun 2026 announced 11 Aug 2026

CoreWeave — Revenue backlog of approximately $104.2bn as at 30 June 2026.

Excludes more than $25bn of net new customer commitments added in early Q3, so the quarter-end figure understates committed demand at the time of reading.

Confirmed high significance new disclosure ↗ investors.coreweave.com
Not disclosed $104.2bn
30 Jun 2026 announced 11 Aug 2026

TeraWulf — Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.

One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.

Confirmed high significance revenue commenced ↗ investors.terawulf.com
Not disclosed 102 MW
30 Jun 2026 announced 11 Aug 2026

Keel Infrastructure — Portfolio split disclosed: 648 MW secured, 1,513 MW planned or in development, approximately 2.2 GW total pipeline.

The 2.2 GW previously carried as secured power is a development pipeline. Secured capacity is 648 MW — under a third of the headline figure.

Confirmed high significance new disclosure ↗ investor.bitfarms.com
Not disclosed 648 MW
30 Jun 2026 announced 11 Aug 2026

Keel Infrastructure — Panther Creek holds 350 MW of contracted firm power with conditional land development approval; environmental permits outstanding.

A worked example of why gates are tracked independently — power and zoning have advanced while environmental approval has not, and the data centre itself is not evidenced as under construction.

Confirmed medium significance stage change ↗ sec.gov
31 Dec 2026 announced 7 Aug 2026

Nebius Group — Year-end contracted-power target raised to 5 GW, from a measured "more than 3.5 GW".

A target, not delivered capacity. The 3.5 GW is the last explicitly measured figure; the 5 GW is an ambition for 31 December 2026 and is excluded from every current-capacity total.

Confirmed high significance target change ↗ assets.nebius.com ↗ sec.gov
3.50 GW 5 GW
5 Aug 2026 announced 5 Aug 2026

Applied Digital — Delta Forge 2: 210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over 15 years.

Under construction with expected delivery in H1 2028 — contracted revenue that does not begin for roughly eighteen months.

Confirmed high significance contract signed ↗ ir.applieddigital.com
1.20 GW 1.41 GW
4 Aug 2026 announced 4 Aug 2026

TeraWulf — Anthropic lease at the Justified Data Campus — approximately 401 MW critical IT, 20-year initial term, approximately $19bn.

Nearly doubles disclosed contracted capacity, but initial capacity is not expected until H2 2027 and full delivery not until early 2028. Contracted is not delivered.

Confirmed high significance contract signed ↗ investors.terawulf.com
438 MW 839 MW
4 Aug 2026 announced 4 Aug 2026

TeraWulf — Sale of TeraWulf's 50.1% interest in the Abernathy joint venture to Fluidstack.

Capacity disposed of must leave current owned totals. This is one reason the February 2.2 GW pipeline figure is retained as historical rather than carried forward as a current value.

Confirmed medium significance disposal ↗ investors.terawulf.com
29 Jul 2026 announced 29 Jul 2026

TeraWulf — FERC authorised the acquisition of Morgantown Power LLC (Docket EC26-58-000).

The first regulator-sourced record on the site, and a useful warning about headline approvals: FERC states the order covers the ownership transfer only. Data centre development, new generation, gas infrastructure, battery storage and any change to PJM participation each require separate review. Company guidance still contemplates data centre operations only in 2030.

Confirmed medium significance stage change ↗ elibrary.ferc.gov
31 May 2026 announced 15 Jul 2026

Applied Digital — 1,410 MW of contracted critical IT across five campuses, approximately $36.2bn of contracted revenue.

The largest disclosed customer-contracted figure of any tracked company, and an exhaustive one — unlike IREN's and TeraWulf's, which are minimums. Replaces a stale 600 MW record.

Confirmed high significance new disclosure ↗ sec.gov
600 MW 1.41 GW
1 Jun 2026 announced 1 Jun 2026

IREN Limited — NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term.

Takes disclosed customer-contracted capacity to a minimum of 260 MW alongside the 200 MW Microsoft contract. Still a minimum — other contracts do not disclose megawatts.

Confirmed high significance contract signed ↗ sec.gov
200 MW 260 MW
1 Jun 2026 announced 1 Jun 2026

IREN Limited — Additional AI developer contracts totalling approximately $2.8bn.

Megawatts not disclosed, which is precisely why the company's customer-contracted figure is carried as a disclosed minimum rather than an exhaustive total.

Confirmed medium significance contract signed ↗ sec.gov
Not disclosed $2.8bn
1 Jun 2026 announced 1 Jun 2026

Nebius Group — Meta agreement: $12bn dedicated-capacity commitment over five years.

A further $15bn may follow, relating to additional or otherwise unsold capacity, for a maximum of approximately $27bn. Only the $12bn is a commitment; the balance is conditional and is not displayed as committed revenue.

Confirmed high significance contract signed ↗ nebius.com
Not disclosed $12bn
Every entry names the document it came from. Where a previous value was never published, the change shows Not disclosed rather than an assumed figure.

Guidance scorecard

Promised against delivered

Delivery against guidance

7 of 23 projects carry a guided date
This is the measurement the site exists for: how long secured power actually takes to become invoicing compute. It needs a promised date and a delivered date, and companies publish far fewer of the first than you would expect.
10
Guided milestones
Dates or windows a company has actually stated
1
Reached and scoreable
Both a target and an actual exist
9
Still outstanding
Guided, not yet reached
0
Missed the window
Delivered after the guided end date
No delivery hit rate is published. Only 1 milestone has both a guided date and a delivered date — below the 3 needed for a rate that means anything. It will appear here as more milestones land.

Contract economics

Compiled from filings
Scroll sideways for all columns →
CompanyCustomerMW TermValueDeliveredTerms
IREN Microsoft 200 MWCritical IT 5 yr $9.7bn 50 MW25% of the contract Five-year average term. Horizon 1 (50 MW) delivered and accepted 13 Aug 2026.Confirmed ↗ sec.gov ↗ globenewswire.com
IREN NVIDIA 60 MWCritical IT 5 yr $3.4bn Not disclosed Five-year term. IREN has not named the site that will serve this agreement.Confirmed ↗ sec.gov
IREN Other AI developer contracts Not disclosed Not disclosed $2.8bn Not disclosed Approximately $2.8bn total contract value. Megawatts not disclosed.Confirmed ↗ sec.gov
CRWV Aggregate revenue backlog Not disclosed Not disclosed $104.2bn Not disclosed Approximately $104.2bn as at 30 Jun 2026. A further $25bn+ of net new customer commitments was added in early Q3 and sits outside this quarter-end figure.Confirmed ↗ investors.coreweave.com
NBIS Meta Platforms Not disclosed 5 yr $12bn committedup to $27bn maximum — the balance is conditional and is not committed revenue Not disclosed $12bn dedicated-capacity commitment over five years, plus up to a further $15bn relating to additional or otherwise unsold capacity. The $27bn maximum is conditional and is not committed revenue.Confirmed ↗ nebius.com
WULF Anthropic (Justified Data Campus) 401 MWCritical IT 20 yr $19bn Not disclosed 20-year initial lease term. Initial capacity expected H2 2027, full delivery expected early 2028.Confirmed ↗ investors.terawulf.com
APLD CoreWeave (Polaris Forge 1) 400 MWCritical IT 15 yr $11bn Not disclosed 15-year initial term.Confirmed ↗ sec.gov
APLD Investment-grade hyperscaler (Polaris Forge 2) 200 MWCritical IT 15 yr $5bn Not disclosed 15-year initial term. Customer not named by the company.Confirmed ↗ sec.gov
APLD High investment-grade hyperscaler (Polaris Forge 3) 300 MWCritical IT 15 yr $7.5bn Not disclosed 15-year initial term. Customer not named by the company.Confirmed ↗ sec.gov
APLD High investment-grade hyperscaler (Delta Forge 1) 300 MWCritical IT 15 yr $7.5bn Not disclosed 15-year initial term. Customer not named by the company.Confirmed ↗ sec.gov
APLD High investment-grade hyperscaler (Delta Forge 2) 210 MWCritical IT 15 yr $5.2bn Not disclosed 15-year initial term. Under construction, expected delivery H1 2028.Confirmed ↗ ir.applieddigital.com

Per-megawatt figures are not comparable across business models, so this table does not rank them.

Delivery by country

Select a country for its sites
Each column is a separate measurement. Gross utility power and critical IT load are never added together, and planned or potential capacity is kept out of both.
Scroll sideways for all columns →
Country Gross utility Critical IT Energised Under construction Planned / potential Unspecified basis
688 MW 3.80 GW 1.99 GW 1.41 GW 2.45 GW
96 MW
310 MW
Total 688 MW3.80 GW 1.99 GW1.41 GW 2.86 GW
5 sites are named in filings without a megawatt figure. They are listed under their country but excluded from every column rather than counted as zero.

Why these figures differ from the company headline

Reconciliation
Companies quote the largest defensible number, which is usually gross utility power including targets and pipeline. T2C reports the comparable measure. Neither is wrong — they answer different questions.
CompanyHeadline figureHow T2C records it
CoreWeave 4.2 GW contracted power Shown as secured power on a gross-utility basis. It is a total that already includes the 1.5 GW active — the two are not additive, and neither is customer-contracted compute.
Nebius 5 GW contracted power That is a year-end target from the Q2 shareholder letter, not capacity held today. The last explicitly measured figure is "more than 3.5 GW", which is what the totals use.
Keel 2.2 GW That is the total development pipeline. The company splits it into 648 MW secured and 1,513 MW planned. Only the 648 MW is counted as secured.
TeraWulf 1 GW at Muskie Up to 1 GW of contracted electric service — power availability at the utility, not customer-contracted critical IT. It is excluded from contracted totals.
IREN 480 MW A 2026 gross AI Cloud capacity target across multiple sites, not construction at one site and not current capacity. Held as a target and excluded from all current totals.
Applied Digital 2.15 GW Gross grid-connected utility power. The comparable customer-contracted figure is 1,410 MW of critical IT — a different measurement of a different thing.

Intelligence

SEC filings

Data health

Audit cut-off 15 Aug 2026
21
Confirmed values
Primary source linked
2
Reported values
Awaiting a primary document
17
Not disclosed
Stored as null, never zero
0
Unsourced
Values with no document at all
23
Projects tracked
62
Evidenced gates
Project gates with a source
16
Ledger events
5
Catalysts
Static data built 2026-08-16T11:46:18Z. Live feed status is shown in the header; analyst coverage is reported in the Scenarios view.

What the terms mean

Reference
Evidence levels
Confirmed

Stated in a primary document — an SEC filing, an official investor-relations release, a shareholder letter, or a regulator/utility record — and that document is linked.

Reported

Attributed to the company but read second-hand, or carried over from an earlier compile whose original document is not linked. News can put a figure here; it can never make one confirmed.

Estimated

Derived rather than disclosed. Shown separately from confirmed figures, with the derivation stated, and never included in a confirmed total.

Not disclosed

The company has not published this figure. It is stored as null and is never treated as zero.

Value types
Actualcounted

A current, operating figure as at the stated date.

Disclosed minimumcounted

At least this much, from the components the company has itemised. The company has not published an exhaustive total, so the real figure may be higher.

Targetexcluded

A management goal for a future date. An intention, not a capability that exists today, and never counted in a current-capacity total.

Pipelineexcluded

Identified development opportunity — sites under study, options held, applications lodged. Not secured and not built.

Potentialexcluded

A theoretical ceiling, typically phrased "up to". Conditional on approvals, financing and demand that do not yet exist.