1.41 GW●ConfirmedCritical IT↗ sec.govas of 31 May 2026
100 MW●ConfirmedCritical IT↗ sec.govas of 31 May 2026
Not disclosed—Not disclosed
100 MW●ConfirmedCritical IT↗ sec.govas of 31 May 2026
15 Aug 2026
Delivery ledger
16 verified events
16 events
13 Aug 2026announced 13 Aug 2026
IREN Limited — Horizon 1 — 50 MW of critical IT — delivered to and accepted by Microsoft.
The only formally accepted hyperscaler capacity across every company tracked here. Acceptance is the milestone that normally starts the revenue clock, but IREN has not separately disclosed that billing has commenced, so it is not recorded as revenue-live.
CoreWeave — Contracted power reached approximately 4.2 GW, up from 3.7 GW at quarter end.
A further 500 MW of supply secured within six weeks of the quarter close. Contracted power is a total that already includes active capacity, so this widens the gap between power controlled and power energised rather than closing it.
CoreWeave — Active power expanded by nearly 500 MW to reach 1.5 GW.
The largest single-quarter energisation step on the board. The previous value is derived from the company's own "expanded by nearly 500 MWs" wording rather than a separately published Q1 figure.
CoreWeave — Revenue backlog of approximately $104.2bn as at 30 June 2026.
Excludes more than $25bn of net new customer commitments added in early Q3, so the quarter-end figure understates committed demand at the time of reading.
TeraWulf — Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.
One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.
Keel Infrastructure — Panther Creek holds 350 MW of contracted firm power with conditional land development approval; environmental permits outstanding.
A worked example of why gates are tracked independently — power and zoning have advanced while environmental approval has not, and the data centre itself is not evidenced as under construction.
Nebius Group — Year-end contracted-power target raised to 5 GW, from a measured "more than 3.5 GW".
A target, not delivered capacity. The 3.5 GW is the last explicitly measured figure; the 5 GW is an ambition for 31 December 2026 and is excluded from every current-capacity total.
TeraWulf — Anthropic lease at the Justified Data Campus — approximately 401 MW critical IT, 20-year initial term, approximately $19bn.
Nearly doubles disclosed contracted capacity, but initial capacity is not expected until H2 2027 and full delivery not until early 2028. Contracted is not delivered.
TeraWulf — Sale of TeraWulf's 50.1% interest in the Abernathy joint venture to Fluidstack.
Capacity disposed of must leave current owned totals. This is one reason the February 2.2 GW pipeline figure is retained as historical rather than carried forward as a current value.
TeraWulf — FERC authorised the acquisition of Morgantown Power LLC (Docket EC26-58-000).
The first regulator-sourced record on the site, and a useful warning about headline approvals: FERC states the order covers the ownership transfer only. Data centre development, new generation, gas infrastructure, battery storage and any change to PJM participation each require separate review. Company guidance still contemplates data centre operations only in 2030.
Applied Digital — 1,410 MW of contracted critical IT across five campuses, approximately $36.2bn of contracted revenue.
The largest disclosed customer-contracted figure of any tracked company, and an exhaustive one — unlike IREN's and TeraWulf's, which are minimums. Replaces a stale 600 MW record.
IREN Limited — NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term.
Takes disclosed customer-contracted capacity to a minimum of 260 MW alongside the 200 MW Microsoft contract. Still a minimum — other contracts do not disclose megawatts.
IREN Limited — Additional AI developer contracts totalling approximately $2.8bn.
Megawatts not disclosed, which is precisely why the company's customer-contracted figure is carried as a disclosed minimum rather than an exhaustive total.
Nebius Group — Meta agreement: $12bn dedicated-capacity commitment over five years.
A further $15bn may follow, relating to additional or otherwise unsold capacity, for a maximum of approximately $27bn. Only the $12bn is a commitment; the balance is conditional and is not displayed as committed revenue.
Every entry names the document it came from. Where a previous value was never
published, the change shows Not disclosed rather than an assumed figure.
Guidance scorecard
Promised against delivered
Delivery against guidance
7 of 23 projects carry a guided date
This is the measurement the site exists for: how long secured power actually
takes to become invoicing compute. It needs a promised date and a delivered date, and companies
publish far fewer of the first than you would expect.
10
Guided milestones
Dates or windows a company has actually stated
1
Reached and scoreable
Both a target and an actual exist
9
Still outstanding
Guided, not yet reached
0
Missed the window
Delivered after the guided end date
No delivery hit rate is published. Only 1 milestone has both a guided date and a delivered date — below the 3 needed for a rate that means anything. It will appear here as more milestones land.
Approximately $104.2bn as at 30 Jun 2026. A further $25bn+ of net new customer commitments was added in early Q3 and sits outside this quarter-end figure.●Confirmed↗ investors.coreweave.com
$12bn committedup to $27bn maximum — the balance is conditional and is not committed revenue
Not disclosed
$12bn dedicated-capacity commitment over five years, plus up to a further $15bn relating to additional or otherwise unsold capacity. The $27bn maximum is conditional and is not committed revenue.●Confirmed↗ nebius.com
15-year initial term. Under construction, expected delivery H1 2028.●Confirmed↗ ir.applieddigital.com
Per-megawatt figures are not comparable across business models, so
this table does not rank them.
Delivery by country
Select a country for its sites
Each column is a separate measurement. Gross utility power and critical IT load
are never added together, and planned or potential capacity is kept out of both.
Hosts the Microsoft Horizon tranches and the NVIDIA deployment. The 480 MW previously shown here is IREN's wider 2026 gross AI Cloud target across multiple sites, not this site's capacity.
Remaining Microsoft tranches — the balance of the 200 MW contract after Horizon 1's 50 MW. Planned, not delivered, and held separately from accepted capacity.
102 MW revenue-generating critical IT plus 336 MW additional critical IT under construction across CB-4 and CB-5. CB-3 delivery completed in early July 2026.
Approximately 401 MW critical IT on a 20-year initial lease, approximately $19bn contracted revenue over the initial term. Initial capacity expected H2 2027, full delivery early 2028.
Up to 1 GW of contracted electric service via Kentucky Power Company. This is power availability at the utility, not customer-contracted critical IT, and is excluded from contracted-capacity totals.
Approximately 210 MW operational generation at the Morgantown Generating Station. A further campus scale of up to 1 GW is potential only and is not current critical IT.
110 MW gross total site capacity: 30 MW existing energised utility capacity plus 80 MW under an energy-services agreement with associated substation work. Not 110 MW of critical IT under construction.
350 MW contracted firm power, of which 60 MW is currently energised. The 10-Q states that Panther Creek's energised capacity sits under NO energy service agreement and is therefore excluded from the company's own secured total — live power is not the same as secured power. The data centre itself is not evidenced as under construction.
CORRECTION: previously shown as 1.3 GW of secured capacity. Load studies and behind-the-meter feasibility work are pipeline and potential, not secured power. 63 MW is currently energised, and the 10-Q states this sits under no energy service agreement — so it is excluded from the company's own secured total.
210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term. Under construction, with initial operations anticipated in Q1 2028.
CORRECTION: 310 MW is the capacity this facility is expected to reach when fully deployed — planned project capacity, not capacity energised today. It was previously counted as current energised critical IT.
5 sites are named in filings without a megawatt figure. They are
listed under their country but excluded from every column rather than counted as zero.
Why these figures differ from the company headline
Reconciliation
Companies quote the largest defensible number, which is usually gross utility
power including targets and pipeline. T2C reports the comparable measure. Neither is wrong — they
answer different questions.
Company
Headline figure
How T2C records it
CoreWeave
4.2 GW contracted power
Shown as secured power on a gross-utility basis. It is a total that already includes the 1.5 GW active — the two are not additive, and neither is customer-contracted compute.
Nebius
5 GW contracted power
That is a year-end target from the Q2 shareholder letter, not capacity held today. The last explicitly measured figure is "more than 3.5 GW", which is what the totals use.
Keel
2.2 GW
That is the total development pipeline. The company splits it into 648 MW secured and 1,513 MW planned. Only the 648 MW is counted as secured.
TeraWulf
1 GW at Muskie
Up to 1 GW of contracted electric service — power availability at the utility, not customer-contracted critical IT. It is excluded from contracted totals.
IREN
480 MW
A 2026 gross AI Cloud capacity target across multiple sites, not construction at one site and not current capacity. Held as a target and excluded from all current totals.
Applied Digital
2.15 GW
Gross grid-connected utility power. The comparable customer-contracted figure is 1,410 MW of critical IT — a different measurement of a different thing.
Intelligence
SEC filings
Data health
Audit cut-off 15 Aug 2026
21
Confirmed values
Primary source linked
2
Reported values
Awaiting a primary document
17
Not disclosed
Stored as null, never zero
0
Unsourced
Values with no document at all
23
Projects tracked
62
Evidenced gates
Project gates with a source
16
Ledger events
5
Catalysts
Static data built 2026-08-16T11:46:18Z. Live feed status is shown in the header;
analyst coverage is reported in the Scenarios view.
What the terms mean
Reference
Evidence levels
●Confirmed
Stated in a primary document — an SEC filing, an official investor-relations release, a shareholder letter, or a regulator/utility record — and that document is linked.
◐Reported
Attributed to the company but read second-hand, or carried over from an earlier compile whose original document is not linked. News can put a figure here; it can never make one confirmed.
◌Estimated
Derived rather than disclosed. Shown separately from confirmed figures, with the derivation stated, and never included in a confirmed total.
—Not disclosed
The company has not published this figure. It is stored as null and is never treated as zero.
Value types
Actual∑counted
A current, operating figure as at the stated date.
Disclosed minimum∑counted
At least this much, from the components the company has itemised. The company has not published an exhaustive total, so the real figure may be higher.
Target⊘excluded
A management goal for a future date. An intention, not a capability that exists today, and never counted in a current-capacity total.
Pipeline⊘excluded
Identified development opportunity — sites under study, options held, applications lodged. Not secured and not built.
Potential⊘excluded
A theoretical ceiling, typically phrased "up to". Conditional on approvals, financing and demand that do not yet exist.