Sites
Every AI data centre T2C tracks: its size, its status, its customer and the latest news naming it. Open a site for what happens next.
Delta Forge 1
🇺🇸 United States300 MW leased to a high investment-grade hyperscaler, approximately $7.5bn over a 15-year initial term.
Delta Forge 2
🇺🇸 United States210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term.
Polaris Forge 1
🇺🇸 United States400 MW leased to CoreWeave, approximately $11bn over a 15-year initial term. 250 MW live as of 1 October 2026.
Polaris Forge 2
🇺🇸 United States200 MW leased to an investment-grade hyperscaler, approximately $5bn over a 15-year initial term.
Polaris Forge 3
🇺🇸 United States300 MW leased to a high investment-grade hyperscaler, approximately $7.5bn over a 15-year initial term.
US data centre estate
🇺🇸 United StatesCoreWeave reports fleet-wide rather than per site; the site-level split is not disclosed.
British Columbia sites
🇨🇦 CanadaLegacy capacity converting to GPU use.
Bundey, South Australia
🇦🇺 AustraliaPart of the 5 GW secured portfolio.
Childress, Texas
🇺🇸 United StatesHosts the Microsoft Horizon tranches and the NVIDIA deployment.
Horizon 1 (Childress)
🇺🇸 United StatesDelivered to and accepted by Microsoft on 13 August 2026.
Horizons 2–4 (Childress)
🇺🇸 United StatesRemaining Microsoft tranches — the balance of the 200 MW contract after Horizon 1's 50 MW.
Spain
🇪🇸 SpainPart of the 5 GW secured portfolio.
Moses Lake, Washington
🇺🇸 United States18 MW gross project capacity.
Panther Creek, Pennsylvania
🇺🇸 United States350 MW contracted firm power, of which 60 MW is currently energised.
Scrubgrass, Pennsylvania
🇺🇸 United StatesCORRECTION: previously shown as 1.3 GW of secured capacity.
Sharon, Pennsylvania
🇺🇸 United States110 MW gross total site capacity: 30 MW existing energised utility capacity plus 80 MW under an energy-services agreement with associated substation…
Sherbrooke, Québec
🇨🇦 Canada96 MW under a conditional transfer and operation agreement.
Kansas City, Missouri
🇺🇸 United StatesUS campus build-out.
Mäntsälä, Finland
🇫🇮 FinlandCORRECTION: 310 MW is the capacity this facility is expected to reach when fully deployed — planned project capacity, not capacity energised today.
Chesapeake (Maryland)
🇺🇸 United StatesApproximately 210 MW operational generation at the Morgantown Generating Station.
Justified Data Campus (Anthropic)
🇺🇸 United StatesApproximately 401 MW critical IT on a 20-year initial lease, approximately $19bn contracted revenue over the initial term.
Lake Mariner, New York
🇺🇸 United States102 MW revenue-generating critical IT plus 336 MW additional critical IT under construction across CB-4 and CB-5.
Muskie (Kentucky)
🇺🇸 United States1 GW of contracted electric service with Kentucky Power, raised from 500 MW on 5 October 2026.
Capacity figures state what they measure, and half this estate quotes gross power at the fence while the other half quotes critical IT in the hall. Where a site publishes only a gross figure, the comparable critical IT load is shown beneath it in amber as a T2C estimate — gross ÷ 1.4 — so the list can be read down one column. A site showing Not disclosed has published nothing to derive from: it is never shown as zero and never filled with a peer average. How estimates work.