IREN Limited IREN

Builds its own data centres and rents out the GPUs inside them.

Follow by RSS
94Reality Score
how it is built
Live now
≥50 MWcritical IT, energised
Signed by customers
≥260 MWcontracted
Billing
≥40 MWdisclosed as earning
Next results
3 Feb 2027date confirmed
Sites
62 live or billing

Where IREN sits in the chain

Each link quotes the filing that discloses it — hover for the sentence, or open IREN on the full chain.

2 new filings not yet reviewed — the figures on this page do not reflect them yet.

  • 5 Nov 2026 10-Q · Quarterly report EDGAR ↗
  • 5 Nov 2026 8-K · Results of operations EDGAR ↗

Latest on the record

  • 27 Aug 2026 IREN reports about 40 MW of AI Cloud capacity operating and $1bn of operating ARR.
  • 27 Aug 2026 Horizon 2 is commissioning and Horizons 3-4 are in late-stage construction, targeting Q4 2026.
  • 27 Aug 2026 New multi-year AI Cloud contract with a leading frontier AI lab.
  • 13 Aug 2026 Horizon 1 — 50 MW of critical IT — delivered to and accepted by Microsoft.

In the news

  1. Loading the latest stories…

What comes next

  • 1 Oct 2026 – 31 Dec 2026 Microsoft Horizons 2–4 — remaining tranches

Sites

News about IREN Limited

  1. Loading the latest stories…

Third-party headlines naming IREN Limited or one of its disclosed suppliers or customers.

Record

Supplier passport What IREN supplies, and how far it has actually got
Chain position AI factory IREN Limited builds and operates the data centres themselves. T2C holds no record of it supplying materials, wafers, chips or photonics.
Commercial momentum Accepted Has capacity a customer has formally accepted.
Evidence confidence 94/100 Strong delivery record

Where it sits

  1. Materials
  2. Wafers
  3. Chips + HBM
  4. Photonics
  5. AI Factory This company
  6. Accepted
  7. Revenue

T2C tracks the delivery end of the chain. The four upstream stages are not tracked for any company, so their emptiness here says nothing about IREN Limited specifically.

What could break the thesis

  • 77% of disclosed contracted capacity sits with Microsoft.
  • 1 disclosed contract states no megawatts, so concentration is measured over part of the book.
  • 1 of seven delivery stages carries no disclosure: Billing.

Assembled from the records, not from opinion: each item names an unresolved gate, a measured concentration, or a disclosure that does not exist.

T2C Reality Score Constructed from sourced records — not a disclosed figure
94 Strong delivery record Derived · how this is calculated
Promise delivery 1 of 1 met 35%
Evidence quality 20 of 24 confirmed 30%
Timeline stability 2 held 20%
Financing Not available Financing is not disclosed as a project milestone. 15%

promise delivery rests on 1 of 1 met; timeline stability rests on 2 held. A small sample moves this score as much as a large one.

Computed over 85% of the score's weight. Financing could not be computed and is excluded rather than counted as passing.

Path to billing Furthest reached anywhere: Accepted
  1. Power Implied
  2. Billing Not disclosed

A stage is marked complete when any of IREN Limited's 6 tracked projects has reached it — this is the furthest the company has got anywhere, not the state of every site. Open a stage to see which sites evidence it.

Capacity truth Four different measurements
5 GW Secured Gross
260 MW Contracted Critical IT
50 MW Energised Critical IT
40 MW Billing Critical IT

These are four separate disclosures on different bases, not four stages of one funnel. Secured power is measured at the utility connection; the rest are critical IT. They are never subtracted from one another.

IREN Limited at a glance

Every figure below is sourced
IREN

IREN owns and operates data centres powered by a large secured electricity portfolio, and sells AI cloud capacity to hyperscalers and AI developers.

Full stack Reached: Billing 1% of controlled power switched on

Where the power goes

Each row states the basis it is measured on
Power secured 5 GW GrossUnder construction not disclosed measurement changes to Critical ITEnergised ≥50 MW Critical ITContracted ≥260 MW Critical ITAccepted 50 MW Critical ITBilling ≥40 MW Critical IT
Each bar is drawn to the same scale. A dashed row means the company has not published that figure — it is not zero. Where the dashed line appears, the measurement itself changes from power at the utility connection to usable capacity inside the hall, so the step down is a change of definition rather than capacity going missing.

What it owns, and what the customer brings

WHO OWNS WHAT Grid power company Building and cooling company Racks and network company Accelerators company Compute sold company
The company owns every layer from grid power through to the accelerators, and sells finished compute.

Where it operates

6 recorded sites
3
1
1
1

A filled dot is a site with a published capacity figure; an outlined dot is a site named in filings without one. Positions are schematic, not geographic.

Capacity record

Every value with its evidence
MeasureValue and evidence
Secured powerPower capacity controlled through executed utility, interconnection, energy-service, lease or comparable arrangements. It may include capacity already operating as well as capacity awaiting development. Secured power indicates supply control, not customer demand or completed compute capacity. 5 GW ConfirmedGross ↗ sec.govas of 30 Jun 2026
Evidence · 1 source

Secured global power portfolio, quoted at the utility connection. Not critical IT and not comparable with a critical-IT figure.

As of
30 Jun 2026
Verified
25 Oct 2026
Basis
Gross utility power
Type
Actual
Coverage
Exhaustive total
IREN Limited annual report, fiscal year ended 30 June 2026 (Form 10-K) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · primary
"As of June 30, 2026, our operating AI Cloud Services capacity represented approximately 40MW." "Executed grid connection agreements ... representing approximately 5GW of total power capacity." "Horizon 2-4 is targeted for delivery in phases in calendar Q4 2026, with grace periods under the Microsoft Agreement for delivery extending from mid-Q4 2026 to the beginning of Q2 2027."
Customer-contractedCompute or capacity a paying customer has committed to under a signed contract. Demand, not supply. Frequently disclosed only for individual named contracts, in which case the site total is a disclosed minimum rather than an exhaustive figure. ≥260 MW ConfirmedDisclosed minimumCritical IT ↗ sec.gov ↗ sec.govas of 1 Jun 2026
Evidence · 2 sources

Microsoft 200 MW plus NVIDIA 60 MW. A disclosed minimum: the further AI developer contracts worth approximately $2.8bn, and the multi-year frontier-lab contract announced with the FY26 results, do not disclose megawatts, so the true total is higher. IREN describes its 2026 capacity as "largely sold out" with $4bn of contracted ARR.

As of
1 Jun 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Disclosed minimum
Coverage
Not exhaustive — may be higher
IREN Limited Form 8-K — Microsoft AI cloud agreement IREN Limited (SEC EDGAR) · sec-filing · published 3 Nov 2025 · primary
Microsoft contract for 200 MW of critical IT capacity, approximately $9.7bn, five-year average term.
IREN Limited Exhibit 99.1 — NVIDIA agreement and AI cloud contracts IREN Limited (SEC EDGAR) · sec-filing · published 1 Jun 2026 · primary
NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term. Additional AI developer contracts totalling approximately $2.8bn.
Energised critical ITCritical IT load live and drawing power. Often described by companies as "active" or "operational" capacity. It does not by itself mean a customer is paying for it. ≥50 MW ConfirmedDisclosed minimumCritical IT ↗ globenewswire.comas of 13 Aug 2026
Evidence · 1 source

Horizon 1 — 50 MW of critical IT delivered and accepted. A disclosed minimum: this is the only tranche with an explicit critical-IT figure, and no company-wide energised total has been published on a comparable basis.

As of
13 Aug 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Disclosed minimum
Coverage
Not exhaustive — may be higher
IREN Delivers Horizon 1 to Microsoft and Achieves NVIDIA Exemplar Cloud Status on GB300 NVL72 IREN Limited via GlobeNewswire · company-ir · published 13 Aug 2026 · primary
Horizon 1, 50 MW of critical IT capacity, delivered to and accepted by Microsoft.
Customer-acceptedCapacity formally accepted under the relevant customer agreement. Acceptance may trigger billing or revenue recognition, but the commercial effect is contract-specific and must be separately evidenced. 50 MW ConfirmedCritical IT ↗ globenewswire.comas of 13 Aug 2026
Evidence · 1 source

Horizon 1 delivered to and accepted by Microsoft on 13 August 2026.

As of
13 Aug 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Exhaustive total
IREN Delivers Horizon 1 to Microsoft and Achieves NVIDIA Exemplar Cloud Status on GB300 NVL72 IREN Limited via GlobeNewswire · company-ir · published 13 Aug 2026 · primary
Horizon 1, 50 MW of critical IT capacity, delivered to and accepted by Microsoft.
Revenue liveCapacity for which the company has explicitly disclosed that billing, rent commencement or revenue generation has begun. Billing, GAAP revenue recognition and cash receipt are not assumed to occur simultaneously. ≥40 MW ConfirmedDisclosed minimumCritical IT ↗ sec.gov ↗ sec.govas of 30 Jun 2026
Evidence · 2 sources

Approximately 40 MW of operating AI Cloud Services capacity at 30 June 2026, which earned $70.5m of AI Cloud revenue in the June quarter. IREN does not state the basis; it quotes its AI Cloud deployments in MW (IT) elsewhere, so it is carried as critical IT. A minimum: it predates Horizon 1, and IREN reported $1bn of operating ARR on 26 August without a megawatt figure. Horizon 1 itself is accepted, but billing on it has not been separately disclosed.

As of
30 Jun 2026
Verified
25 Oct 2026
Basis
Critical IT load
Type
Disclosed minimum
Coverage
Not exhaustive — may be higher
IREN Limited annual report, fiscal year ended 30 June 2026 (Form 10-K) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · primary
"As of June 30, 2026, our operating AI Cloud Services capacity represented approximately 40MW." "Executed grid connection agreements ... representing approximately 5GW of total power capacity." "Horizon 2-4 is targeted for delivery in phases in calendar Q4 2026, with grace periods under the Microsoft Agreement for delivery extending from mid-Q4 2026 to the beginning of Q2 2027."
IREN Reports FY26 Results (Exhibit 99.1) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · primary
"$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.

Not disclosed by IREN Limited: Development pipeline, Under construction.

Targets

Management goals — excluded from all current totals
Energised critical IT targetTargeted cumulative delivery of approximately 0.3 GW (IT) by the end of 2026. Excluded from every current-capacity total. 300 MW ConfirmedTargetCritical IT ↗ sec.govas of 31 Dec 2026
Evidence · 1 source

Targeted cumulative delivery of approximately 0.3 GW (IT) by the end of 2026. Excluded from every current-capacity total.

As of
31 Dec 2026
Verified
25 Oct 2026
Basis
Critical IT load
Type
Target
Coverage
Not exhaustive — may be higher
IREN Reports FY26 Results (Exhibit 99.1) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · primary
"$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.
Energised critical IT targetTargeted cumulative delivery of approximately 0.8 GW (IT) by the end of 2027. 800 MW ConfirmedTargetCritical IT ↗ sec.govas of 31 Dec 2027
Evidence · 1 source

Targeted cumulative delivery of approximately 0.8 GW (IT) by the end of 2027.

As of
31 Dec 2027
Verified
25 Oct 2026
Basis
Critical IT load
Type
Target
Coverage
Not exhaustive — may be higher
IREN Reports FY26 Results (Exhibit 99.1) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · primary
"$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.

Superseded disclosures

Retained and dated, not deleted
Under constructionHistorical disclosure — superseded 480 MW ConfirmedTargetGross ↗ sec.govas of 31 Dec 2026
Evidence · 1 source

May 2026 target of 480 MW gross AI Cloud capacity for 2026. Superseded by the FY26 results, which restate the target as 0.3 GW of critical IT.

As of
31 Dec 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Target
Coverage
Not exhaustive — may be higher
IREN Reports Q3 FY26 Results IREN Limited (SEC EDGAR) · sec-filing · published 31 Mar 2026 · primary
"...as we scale across our global 5GW secured power portfolio." Also: "2026 expansion to 480MW on track — Horizon 1-4 on track for delivery by year-end", and "2028+ expansion across 5GW secured power underway". Confirms 480 MW is a 2026 expansion target across multiple sites, not construction at one site.
Contract X-ray 3 disclosed agreements
Microsoft 200 MW
Firm
$9.7bn

5-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
50 MW

Accepted by the customer under this agreement.

Five-year average term. Horizon 1 (50 MW) delivered and accepted 13 Aug 2026.

NVIDIA 60 MW
Firm
$3.4bn

5-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

Five-year term. IREN has not named the site that will serve this agreement.

Other AI developer contracts MW not disclosed
Firm
$2.8bn

Committed value.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

Approximately $2.8bn total contract value. Megawatts not disclosed.

Committed value and conditional maximum are shown apart and never added. Where a company discloses a ceiling — "up to" — the difference depends on events that have not happened.

Contract detail

Every disclosed field
Scroll sideways for all columns →
CustomerMWTerm ValueDeliveredTerms
Microsoft 200 MWCritical IT 5 yr $9.7bn 50 MW Five-year average term. Horizon 1 (50 MW) delivered and accepted 13 Aug 2026.↗ sec.gov ↗ globenewswire.com
NVIDIA 60 MWCritical IT 5 yr $3.4bn Not disclosed Five-year term. IREN has not named the site that will serve this agreement.↗ sec.gov
Other AI developer contracts Not disclosed Not disclosed $2.8bn Not disclosed Approximately $2.8bn total contract value. Megawatts not disclosed.↗ sec.gov

Verified changes

6 events
30 Jun 2026announced 27 Aug 2026

IREN reports about 40 MW of AI Cloud capacity operating and $1bn of operating ARR.

The first disclosed billing figure for IREN: roughly 40 MW was earning AI Cloud revenue at 30 June, before Horizon 1 was delivered. Billing on Horizon 1 itself is still not separately disclosed.

Not disclosed40 MW
27 Aug 2026announced 27 Aug 2026

Horizon 2 is commissioning and Horizons 3-4 are in late-stage construction, targeting Q4 2026.

The remaining 150 MW of the Microsoft contract is guided for Q4 2026, with contractual grace periods running to the beginning of Q2 2027.

Not disclosedNot disclosed
27 Aug 2026announced 27 Aug 2026

New multi-year AI Cloud contract with a leading frontier AI lab.

Neither the customer nor the megawatts are disclosed, so the 260 MW contracted figure stays a minimum.

Confirmed↗ sec.gov
Not disclosedNot disclosed
13 Aug 2026announced 13 Aug 2026

Horizon 1 — 50 MW of critical IT — delivered to and accepted by Microsoft.

The only formally accepted hyperscaler capacity across every company tracked here. Acceptance is the milestone that normally starts the revenue clock, but IREN has not separately disclosed that billing on Horizon 1 has commenced, so this site is not recorded as revenue-live.

Not disclosed50 MW
1 Jun 2026announced 1 Jun 2026

NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term.

Takes disclosed customer-contracted capacity to a minimum of 260 MW alongside the 200 MW Microsoft contract. Still a minimum — other contracts do not disclose megawatts.

Confirmed↗ sec.gov
200 MW260 MW
1 Jun 2026announced 1 Jun 2026

Additional AI developer contracts totalling approximately $2.8bn.

Megawatts not disclosed, which is precisely why the company's customer-contracted figure is carried as a disclosed minimum rather than an exhaustive total.

Confirmed↗ sec.gov
Not disclosed$2.8bn

Upcoming catalysts

1
IREN

Microsoft Horizons 2–4 — remaining tranches

The remaining 150 MW of the 200 MW Microsoft contract. Targeted for delivery in phases in Q4 2026; Horizon 2 was commissioning at the FY26 results. Contractual grace periods run from mid-Q4 2026 to the beginning of Q2 2027, so a Q1 2027 delivery would not be a breach.

About IREN

Last verified 15 Aug 2026

IREN owns and operates data centres powered by a large secured electricity portfolio, and sells AI cloud capacity to hyperscalers and AI developers.

IREN is an Australian-listed operator that secures grid power at scale, builds data centres on that power, and increasingly sells finished GPU compute rather than leasing empty space. It converted from bitcoin mining infrastructure toward AI cloud, and is currently the only company tracked here with a hyperscaler tranche formally delivered and accepted.

Company facts

Legal name
IREN Limited
Ticker / exchange
IREN · NASDAQ
Founded
Not disclosed
Headquarters
Sydney, New South Wales, Australia
Business model
Full stack
Last verified
15 Aug 2026

Who leads it

This company is led by co-chief executives. Both are recorded; neither is presented as the sole CEO.
Daniel Roberts
Co-Founder and Co-Chief Executive Officer

Co-founder and co-CEO of IREN, and a director of the company. Background in finance, infrastructure and renewables.

↗ iren.com ↗ sec.govverified 15 Aug 2026
Will Roberts
Co-Founder and Co-Chief Executive Officer

Co-founder and co-CEO of IREN, and a director of the company. Background in finance, real assets and commodities markets.

↗ iren.com ↗ sec.govverified 15 Aug 2026

What it sells

  • AI cloud compute sold by contract to hyperscalers and AI developers
  • Owned and operated data centres built on self-secured grid power
  • Bitcoin mining from earlier operations

How it makes money

Owns the accelerators and sells finished compute. Captures far more revenue per megawatt, and carries the chip capital cost and obsolescence risk to match.

Where it operates

  • United States (Texas)
  • Canada (British Columbia)
  • Australia
  • Spain

Operating presence as disclosed. This is not the same as future pipeline — a named location may hold nothing but secured power.

Publicly disclosed customers

  • Microsoft
  • NVIDIA

Only customers the company has named publicly. Several tracked companies describe counterparties only as "investment-grade hyperscaler", and those are not guessed at here.

Official links

Social accounts are shown only where the link was found on a company-controlled domain. A verification badge alone is not treated as evidence.

Sources

7 documents
  • IREN Limited annual report, fiscal year ended 30 June 2026 (Form 10-K) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · accessed 25 Oct 2026 · primary
    "As of June 30, 2026, our operating AI Cloud Services capacity represented approximately 40MW." "Executed grid connection agreements ... representing approximately 5GW of total power capacity." "Horizon 2-4 is targeted for delivery in phases in calendar Q4 2026, with grace periods under the Microsoft Agreement for delivery extending from mid-Q4 2026 to the beginning of Q2 2027."
  • IREN Reports FY26 Results (Exhibit 99.1) IREN Limited (SEC EDGAR) · sec-filing · published 27 Aug 2026 · accessed 25 Oct 2026 · primary
    "$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.
  • IREN Delivers Horizon 1 to Microsoft and Achieves NVIDIA Exemplar Cloud Status on GB300 NVL72 IREN Limited via GlobeNewswire · company-ir · published 13 Aug 2026 · accessed 15 Aug 2026 · primary
    Horizon 1, 50 MW of critical IT capacity, delivered to and accepted by Microsoft.
  • IREN Limited Exhibit 99.1 — NVIDIA agreement and AI cloud contracts IREN Limited (SEC EDGAR) · sec-filing · published 1 Jun 2026 · accessed 15 Aug 2026 · primary
    NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term. Additional AI developer contracts totalling approximately $2.8bn.
  • IREN Reports Q3 FY26 Results IREN Limited (SEC EDGAR) · sec-filing · published 31 Mar 2026 · accessed 15 Aug 2026 · primary
    "...as we scale across our global 5GW secured power portfolio." Also: "2026 expansion to 480MW on track — Horizon 1-4 on track for delivery by year-end", and "2028+ expansion across 5GW secured power underway". Confirms 480 MW is a 2026 expansion target across multiple sites, not construction at one site.
  • IREN Limited quarterly report, period ended 31 March 2026 IREN Limited (SEC EDGAR) · sec-filing · published 31 Mar 2026 · accessed 15 Aug 2026 · primary
  • IREN Limited Form 8-K — Microsoft AI cloud agreement IREN Limited (SEC EDGAR) · sec-filing · published 3 Nov 2025 · accessed 15 Aug 2026 · primary
    Microsoft contract for 200 MW of critical IT capacity, approximately $9.7bn, five-year average term.