GPU clouds and compute operators

Nebius Group NBIS

An AI cloud with its own data centres in Europe and the US.

Follow by RSS
—Reality Score withheld
not enough record yet
Live now
Not disclosedcritical IT, energised
Signed by customers
Not disclosedcontracted
Billing
Not discloseddisclosed as earning
Next results
10 Feb 2027date confirmed
Sites
20 live or billing

Where Nebius sits in the chain

Sells to

Those customers build Copilot, GitHub Copilot, Muse, Meta AI

Each link quotes the filing that discloses it — hover for the sentence, or open NBIS on the full chain.

2 new filings not yet reviewed — the figures on this page do not reflect them yet.

  • 12 Nov 2026 6-K · Foreign issuer report EDGAR ↗
  • 12 Nov 2026 6-K · Foreign issuer report EDGAR ↗

Latest on the record

  • 22 Oct 2026 Nebius secures a $3.5bn senior secured facility from Citi.
  • 24 Aug 2026 Nebius closes about $5.75bn of convertible senior notes due 2030 and 2034.
  • 7 Aug 2026 Year-end contracted-power target raised to 5 GW, from a measured "more than 3.5 GW".
  • 1 Jun 2026 Meta agreement: $12bn dedicated-capacity commitment over five years.

In the news

  1. Loading the latest stories…

What comes next

  • 1 Oct 2026 – 31 Dec 2026 Nebius year-end 5 GW contracted-power target

Sites

News about Nebius Group

  1. Loading the latest stories…

Third-party headlines naming Nebius Group or one of its disclosed suppliers or customers.

Record

Supplier passport What NBIS supplies, and how far it has actually got
Chain position AI factory Nebius Group builds and operates the data centres themselves. T2C holds no record of it supplying materials, wafers, chips or photonics.
Commercial momentum Under construction Has construction under way.
Evidence confidence Unavailable Too little published record to score — see the breakdown below.

Where it sits

  1. Materials
  2. Wafers
  3. Chips + HBM
  4. Photonics
  5. AI Factory This company
  6. Accepted
  7. Revenue

T2C tracks the delivery end of the chain. The four upstream stages are not tracked for any company, so their emptiness here says nothing about Nebius Group specifically.

What could break the thesis

  • No billing capacity is disclosed, so revenue timing cannot be evidenced.
  • 2 of seven delivery stages carry no disclosure: Accepted, Billing.
  • A Reality Score cannot be computed: Only 1 of 4 factors can be computed from what this company has published, covering 30% of the score's weight.

Assembled from the records, not from opinion: each item names an unresolved gate, a measured concentration, or a disclosure that does not exist.

T2C Reality Score Constructed from sourced records — not a disclosed figure
— Not enough published record to score what would be needed

Only 1 of 4 factors can be computed from what this company has published, covering 30% of the score's weight. A composite below 60% coverage is withheld rather than shown with the gaps treated as passes.

Promise delivery Not available No guided milestone has been reached yet, so there is nothing to score. 35%
Evidence quality 4 of 7 confirmed 30%
Timeline stability Not available This company has guided no dated milestone. 20%
Financing Not available Financing is not disclosed as a project milestone. 15%
Path to billing Furthest reached anywhere: Under construction
  1. Power Implied
  2. Accepted Not disclosed
  3. Billing Not disclosed

A stage is marked complete when any of Nebius Group's 2 tracked projects has reached it — this is the furthest the company has got anywhere, not the state of every site. Open a stage to see which sites evidence it.

Capacity truth Four different measurements
3.50 GW Secured Gross
Not disclosed Contracted N/A Nothing published to derive from
Not disclosed Energised N/A Nothing published to derive from
Not disclosed Billing N/A Nothing published to derive from

These are four separate disclosures on different bases, not four stages of one funnel. Secured power is measured at the utility connection; the rest are critical IT. They are never subtracted from one another.

Nebius Group at a glance

Every figure below is sourced
NBIS

Nebius builds and operates AI cloud infrastructure in Europe and the United States, selling GPU compute to AI developers and large technology customers.

Full stack Reached: Building

Where the power goes

Each row states the basis it is measured on
Power secured ≥3.50 GW GrossUnder construction not disclosedEnergised not disclosedContracted not disclosedAccepted not disclosedBilling not disclosed
Each bar is drawn to the same scale. A dashed row means the company has not published that figure — it is not zero. Where the dashed line appears, the measurement itself changes from power at the utility connection to usable capacity inside the hall, so the step down is a change of definition rather than capacity going missing.

What it owns, and what the customer brings

WHO OWNS WHAT Grid power company Building and cooling company Racks and network company Accelerators company Compute sold company
The company owns every layer from grid power through to the accelerators, and sells finished compute.

Where it operates

2 recorded sites
1
1

A filled dot is a site with a published capacity figure; an outlined dot is a site named in filings without one. Positions are schematic, not geographic.

Capacity record

Every value with its evidence
MeasureValue and evidence
Secured powerPower capacity controlled through executed utility, interconnection, energy-service, lease or comparable arrangements. It may include capacity already operating as well as capacity awaiting development. Secured power indicates supply control, not customer demand or completed compute capacity. ≥3.50 GW ConfirmedDisclosed minimumGross ↗ sec.govas of 31 Mar 2026
Evidence · 1 source

Stated as "more than 3.5 GW" — the latest explicitly measured contracted-power figure before Q2. Recorded as a minimum because the disclosure is a floor, not a total.

As of
31 Mar 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Disclosed minimum
Coverage
Not exhaustive — may be higher
Nebius Group Exhibit 99.1 — Q1 2026 results Nebius Group N.V. (SEC EDGAR) · sec-filing · published 1 May 2026 · primary
Contracted power stated as more than 3.5 GW.

Not disclosed by Nebius Group: Development pipeline, Customer-contracted, Under construction, Energised critical IT, Customer-accepted, Revenue live.

Targets

Management goals — excluded from all current totals
Secured power targetYear-end contracted-power target raised to 5 GW in the Q2 2026 shareholder letter. A goal, not current capacity. 5 GW ConfirmedTargetGross ↗ assets.nebius.comas of 31 Dec 2026
Evidence · 1 source

Year-end contracted-power target raised to 5 GW in the Q2 2026 shareholder letter. A goal, not current capacity.

As of
31 Dec 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Target
Coverage
Not exhaustive — may be higher
Nebius Group Q2 2026 shareholder letter Nebius Group N.V. · company-ir · published 7 Aug 2026 · primary
Year-end contracted power target raised to 5 GW.
Contract X-ray 1 disclosed agreement
Meta Platforms MW not disclosed
Firm
$12bn

5-year term, committed.

Optional
$15bn

Conditional on events that have not occurred. Never added to committed revenue.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

$12bn dedicated-capacity commitment over five years, plus up to a further $15bn relating to additional or otherwise unsold capacity. The $27bn maximum is conditional and is not committed revenue.

Committed value and conditional maximum are shown apart and never added. Where a company discloses a ceiling — "up to" — the difference depends on events that have not happened.

Contract detail

Every disclosed field
Scroll sideways for all columns →
CustomerMWTerm ValueDeliveredTerms
Meta Platforms Not disclosed 5 yr $12bn committedup to $27bn maximum — conditional, not committed revenue Not disclosed $12bn dedicated-capacity commitment over five years, plus up to a further $15bn relating to additional or otherwise unsold capacity. The $27bn maximum is conditional and is not committed revenue.↗ nebius.com

Verified changes

4 events
22 Oct 2026announced 22 Oct 2026

Nebius secures a $3.5bn senior secured facility from Citi.

Capital for the capacity build-out. It changes no tracked megawatt figure.

Confirmed↗ sec.gov
Not disclosed$3.5bn
24 Aug 2026announced 24 Aug 2026

Nebius closes about $5.75bn of convertible senior notes due 2030 and 2034.

Financing only. It changes no tracked megawatt figure.

Confirmed↗ sec.gov
Not disclosed$5.75bn
31 Dec 2026announced 7 Aug 2026

Year-end contracted-power target raised to 5 GW, from a measured "more than 3.5 GW".

A target, not delivered capacity. The 3.5 GW is the last explicitly measured figure; the 5 GW is an ambition for 31 December 2026 and is excluded from every current-capacity total.

3.50 GW5 GW
1 Jun 2026announced 1 Jun 2026

Meta agreement: $12bn dedicated-capacity commitment over five years.

A further $15bn may follow, relating to additional or otherwise unsold capacity, for a maximum of approximately $27bn. Only the $12bn is a commitment; the balance is conditional and is not displayed as committed revenue.

Confirmed↗ nebius.com
Not disclosed$12bn

Upcoming catalysts

1
NBIS

Nebius year-end 5 GW contracted-power target

Management target to reach 5 GW of contracted power by year end, raised from a measured "more than 3.5 GW". A target date for a target figure — it is not a scheduled event and its achievement is not assured.

About Nebius

Last verified 15 Aug 2026

Nebius builds and operates AI cloud infrastructure in Europe and the United States, selling GPU compute to AI developers and large technology customers.

Nebius is a European full-stack AI infrastructure operator. It builds its own data centres, owns the accelerators inside them and sells compute capacity directly. Its original Finnish site is being expanded while a large US campus is developed, and management has set a materially raised contracted-power target for year end.

Company facts

Legal name
Nebius Group N.V.
Ticker / exchange
NBIS · NASDAQ
Founded
Not disclosed
Headquarters
Amsterdam, Netherlands
Business model
Full stack
Last verified
15 Aug 2026

Who leads it

Arkady Volozh
Founder and Chief Executive Officer
In role since 1 Aug 2024

Founder of the group and Chief Executive Officer since August 2024.

↗ nebius.comverified 15 Aug 2026

What it sells

  • AI cloud compute and GPU clusters
  • Owned and operated AI data centres
  • Developer platform and managed services

How it makes money

Owns the accelerators and sells finished compute. Captures far more revenue per megawatt, and carries the chip capital cost and obsolescence risk to match.

Where it operates

  • Finland
  • United States (Missouri)
  • Netherlands

Operating presence as disclosed. This is not the same as future pipeline — a named location may hold nothing but secured power.

Publicly disclosed customers

  • Meta Platforms

Only customers the company has named publicly. Several tracked companies describe counterparties only as "investment-grade hyperscaler", and those are not guessed at here.

Official links

Social accounts are shown only where the link was found on a company-controlled domain. A verification badge alone is not treated as evidence.

Sources

3 documents