Catalysts
Earnings calendar
When the companies across the AI supply chain report next. Results are where capacity,
contracts and delivery dates get updated — so these are the dates most likely to move the record.
Loading dates…
Neoclouds, AI infrastructure and NVIDIA
Across the supply chain
Later reports
Dates are exchange-scheduled events from the provider's earnings calendar, not company
guidance. “Touches” lists operators linked to the reporting company by a filing — exposure, not a
prediction of the result, and never investment advice.
What has already moved the chain
What has already moved it, and what could move it next. Every sourced change
to the record, written as what happened, why it matters and what may happen next —
followed by the dated events still ahead.
(In simple terms: the things that actually move a project forward, and
nothing else.)
Lead signal
Lead signal
Evidence
TeraWulf arranges $0.4bn of financing
? What happened
TeraWulf raises its revolving credit facility from $250m to about $400m.
✓ Why it matters
Financing only. It changes no tracked megawatt figure.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
7 Oct 2026HighAdvanced
Applied Digital adds 150 MW of energised critical IT
? What happened
Applied Digital brings Polaris Forge 1 to 250 MW of live critical IT.
✓ Why it matters
Building 2 was delivered in two 75 MW phases, on 1 July and 1 October. Rent commencement on Building 2 is not separately stated, so billing stays recorded at the 100 MW first building.
Applied Digital Reports Fiscal First Quarter 2027 Results (Exhibit 99.1)Applied Digital Corporation (SEC EDGAR) · 7 Oct 2026
· Primary"On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW." Leases for approximately 1.41 GW of critical IT across five campuses, approximately $36bn over initial base terms. Expects initial operations at Polaris Forge 2 to bring delivered critical IT load across the North Dakota campuses to 300 MW by the end of calendar 2026.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
5 Oct 2026MediumAdvanced
TeraWulf adds 500 MW of secured power
? What happened
TeraWulf doubles contracted power at Muskie to 1 GW and brings the second phase forward to 2029.
✓ Why it matters
Power at the utility, not customer capacity: no tenant is announced. The amendment still needs Kentucky PSC approval, and the first 500 MW is targeted to begin ramping in 2028.
→ What may happen next
Under construction is the next gate. No date or window has been guided for it.
TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW (Exhibit 99.1)TeraWulf Inc. (SEC EDGAR) · 5 Oct 2026
· PrimaryAmended and restated electric service agreement with Kentucky Power increasing contracted power capacity at Muskie from 500 MW to 1 GW; second 500 MW phase advanced from 2030 to 2029, subject to Kentucky PSC approval. First 500 MW phase remains targeted to begin ramping in 2028.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
17 Sep 2026LowEvidence
CoreWeave arranges $3bn of financing
? What happened
CoreWeave offers $3.0bn of convertible senior notes due 2033.
✓ Why it matters
Financing only. The accompanying presentation restates ~1.5 GW active and ~4.2 GW contracted power, unchanged since August.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
27 Aug 2026HighAdvanced
2 records · 1 disclosure
IREN Limited begins earning on 40 MW of critical IT
? What happened
IREN reports about 40 MW of AI Cloud capacity operating and $1bn of operating ARR.
✓ Why it matters
The first disclosed billing figure for IREN: roughly 40 MW was earning AI Cloud revenue at 30 June, before Horizon 1 was delivered. Billing on Horizon 1 itself is still not separately disclosed.
IREN Limited annual report, fiscal year ended 30 June 2026 (Form 10-K)IREN Limited (SEC EDGAR) · 27 Aug 2026
· Primary"As of June 30, 2026, our operating AI Cloud Services capacity represented approximately 40MW." "Executed grid connection agreements ... representing approximately 5GW of total power capacity." "Horizon 2-4 is targeted for delivery in phases in calendar Q4 2026, with grace periods under the Microsoft Agreement for delivery extending from mid-Q4 2026 to the beginning of Q2 2027."
IREN Reports FY26 Results (Exhibit 99.1)IREN Limited (SEC EDGAR) · 27 Aug 2026
· Primary"$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
27 Aug 2026MediumNew contract
IREN Limited signs a new customer contract
? What happened
New multi-year AI Cloud contract with a leading frontier AI lab.
✓ Why it matters
Neither the customer nor the megawatts are disclosed, so the 260 MW contracted figure stays a minimum.
IREN Reports FY26 Results (Exhibit 99.1)IREN Limited (SEC EDGAR) · 27 Aug 2026
· Primary"$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
24 Aug 2026LowEvidence
Nebius Group arranges $5.75bn of financing
? What happened
Nebius closes about $5.75bn of convertible senior notes due 2030 and 2034.
✓ Why it matters
Financing only. It changes no tracked megawatt figure.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
13 Aug 2026HighAdvanced
Microsoft accepts IREN's first 50 MW AI deployment
? What happened
Horizon 1 — 50 MW of critical IT — delivered to and accepted by Microsoft.
✓ Why it matters
The only formally accepted hyperscaler capacity across every company tracked here. Acceptance is the milestone that normally starts the revenue clock, but IREN has not separately disclosed that billing on Horizon 1 has commenced, so this site is not recorded as revenue-live.
→ What may happen next
Billing is the next gate. No date or window has been guided for it.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
11 Aug 2026HighAdvanced
CoreWeave adds 500 MW of secured power
? What happened
Contracted power reached approximately 4.2 GW, up from 3.7 GW at quarter end.
✓ Why it matters
A further 500 MW of supply secured within six weeks of the quarter close. Contracted power is a total that already includes active capacity, so this widens the gap between power controlled and power energised rather than closing it.
→ What may happen next
Accepted is the next gate. No date or window has been guided for it.
CoreWeave Reports Strong Second Quarter 2026 ResultsCoreWeave, Inc. · 11 Aug 2026
· PrimaryExpanded active power by nearly 500 MWs to reach 1.5 GW. Grew total contracted power to approximately 3.7 GW. Revenue backlog was approximately $104bn as of June 30, 2026.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
11 Aug 2026HighAdvanced
2 records · 1 disclosure
CoreWeave adds 500 MW of energised critical IT
? What happened
Active power expanded by nearly 500 MW to reach 1.5 GW.
✓ Why it matters
The largest single-quarter energisation step on the board. The previous value is derived from the company's own "expanded by nearly 500 MWs" wording rather than a separately published Q1 figure.
→ What may happen next
Accepted is the next gate. No date or window has been guided for it.
CoreWeave Reports Strong Second Quarter 2026 ResultsCoreWeave, Inc. · 11 Aug 2026
· PrimaryExpanded active power by nearly 500 MWs to reach 1.5 GW. Grew total contracted power to approximately 3.7 GW. Revenue backlog was approximately $104bn as of June 30, 2026.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
11 Aug 2026HighEvidence
Keel Infrastructure publishes a new disclosure
? What happened
Portfolio split disclosed: 648 MW secured, 1,513 MW planned or in development, approximately 2.2 GW total pipeline.
✓ Why it matters
The 2.2 GW previously carried as secured power is a development pipeline. Secured capacity is 648 MW — under a third of the headline figure.
Keel Infrastructure Reports Second Quarter 2026 ResultsKeel Infrastructure · 11 Aug 2026
· Primary"With a development pipeline of 2.2 gigawatts and established grid interconnections in place." Also: "uncommitted 2027 capacity across PJM and Washington", zoning and land development approvals secured at Panther Creek, environmental permit applications progressing at Sharon, and first Vertiv modules delivered at Moses Lake. This release carries the rounded pipeline and the permitting narrative only; the itemised capacity table is in the Form 10-Q.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
11 Aug 2026HighAdvanced
TeraWulf begins earning on 102 MW of critical IT
? What happened
Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.
✓ Why it matters
One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.
TeraWulf Reports Second Quarter 2026 ResultsTeraWulf Inc. · 11 Aug 2026
· PrimaryLake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
11 Aug 2026MediumAdvanced
Keel Infrastructure passes a delivery milestone
? What happened
Panther Creek holds 350 MW of contracted firm power with conditional land development approval; environmental permits outstanding.
✓ Why it matters
A worked example of why gates are tracked independently — power and zoning have advanced while environmental approval has not, and the data centre itself is not evidenced as under construction.
→ What may happen next
Under construction is the next gate. No date or window has been guided for it.
Keel Infrastructure quarterly report (Form 10-Q)Keel Infrastructure (SEC EDGAR) · 11 Aug 2026
· PrimaryCurrent Energized Capacity 341 MW; Secured Growth Capacity 430 MW; Secured Gross Data Center Capacity 648 MW; Identified Additional Gross Data Center Capacity 1,513 MW; Total Pipeline 2,161 MW. "Secured Gross Data Center Capacity represents the total amount of gross power capacity that is subject to electric supply agreements with utilities, including both power capacity currently available on site and power capacity that utilities have agreed to deliver at a future date." Footnote: "The current energized capacity at the Panther Creek and Scrubgrass site of 60 MW and 63 MW, respectively, are not under an energy service agreement. The capacity is therefore excluded from Secured Gross Data Center Capacity."
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
7 Aug 2026HighOutlook
Nebius Group raises its target to 5 GW
? What happened
Year-end contracted-power target raised to 5 GW, from a measured "more than 3.5 GW".
✓ Why it matters
A target, not delivered capacity. The 3.5 GW is the last explicitly measured figure; the 5 GW is an ambition for 31 December 2026 and is excluded from every current-capacity total.
Applied Digital Signs 210 MW Lease at Delta Forge 2Applied Digital Corporation · 5 Aug 2026
· Primary210 MW lease with a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term, under construction with expected delivery in H1 2028.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
4 Aug 2026HighNew contract
2 records · 1 disclosure
WULF signs Anthropic (Justified Data Campus) for 839 MW
? What happened
Anthropic lease at the Justified Data Campus — approximately 401 MW critical IT, 20-year initial term, approximately $19bn.
✓ Why it matters
Nearly doubles disclosed contracted capacity, but initial capacity is not expected until H2 2027 and full delivery not until early 2028. Contracted is not delivered.
→ What may happen next
Power secured is the next gate. No date or window has been guided for it.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
29 Jul 2026MediumAdvanced
TeraWulf passes a delivery milestone
? What happened
FERC authorised the acquisition of Morgantown Power LLC (Docket EC26-58-000).
✓ Why it matters
The first regulator-sourced record on the site, and a useful warning about headline approvals: FERC states the order covers the ownership transfer only. Data centre development, new generation, gas infrastructure, battery storage and any change to PJM participation each require separate review. Company guidance still contemplates data centre operations only in 2030.
→ What may happen next
Accepted is the next gate. No date or window has been guided for it.
FERC Order authorising acquisition of Morgantown Power LLC — 196 FERC ¶ 61,075, Docket EC26-58-000Federal Energy Regulatory Commission · 29 Jul 2026
· PrimaryAuthorises Chesapeake Data LLC, a wholly owned TeraWulf subsidiary, to acquire 100% of Morgantown Power LLC from Lanyard Power Holdings LLC, finding the transfer consistent with the public interest. Morgantown Power owns four operating oil-fired generating units totalling approximately 216 MW. The authorisation covers the ownership transfer ONLY: data centre development, new generation, gas infrastructure, battery storage and changes to PJM participation each require separate review.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
15 Jul 2026HighEvidence
Applied Digital publishes a new disclosure
? What happened
1,410 MW of contracted critical IT across five campuses, approximately $36.2bn of contracted revenue.
✓ Why it matters
The largest disclosed customer-contracted figure of any tracked company, and an exhaustive one — unlike IREN's and TeraWulf's, which are minimums. Replaces a stale 600 MW record.
Applied Digital Corporation annual report, fiscal year ended 31 May 2026Applied Digital Corporation (SEC EDGAR) · 15 Jul 2026
· Primary1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
1 Jun 2026HighNew contract
2 records · 1 disclosure
IREN Limited signs a customer for 260 MW
? What happened
NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term.
✓ Why it matters
Takes disclosed customer-contracted capacity to a minimum of 260 MW alongside the 200 MW Microsoft contract. Still a minimum — other contracts do not disclose megawatts.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
1 Jun 2026HighNew contract
Nebius Group signs a new customer contract
? What happened
Meta agreement: $12bn dedicated-capacity commitment over five years.
✓ Why it matters
A further $15bn may follow, relating to additional or otherwise unsold capacity, for a maximum of approximately $27bn. Only the $12bn is a commitment; the balance is conditional and is not displayed as committed revenue.
Nebius signs new AI infrastructure agreement with MetaNebius Group N.V. · 1 Jun 2026
· Primary$12bn dedicated-capacity commitment over five years, with up to a further $15bn relating to additional or otherwise unsold capacity — a maximum possible value of approximately $27bn.
T2C records what the document says. It does not verify the underlying event
independently. How evidence is graded
✓
You're caught up
You have reviewed every signal in the latest set. This is the whole record, not the
first page of one — there is nothing more to load.
25 records come from 21 disclosures.
4 documents produced more than one record — a quarterly
release that moves two figures at once is one disclosure, not two events.
This is the only grouping rule applied: records resting on exactly the
same document are one disclosure. T2C does not group by matching headlines, because deciding
that two differently-worded announcements are "really" the same story is a judgement it cannot
evidence. Corrections are never folded into the record they correct.
Read the methodology
Want the raw metric movements rather than the write-up?
The intelligence ledger carries the same records
with every figure and its previous value. For third-party headlines T2C has not verified,
see AI news.
What could move it next
9 dated catalysts
Dated events that could move an operational metric, with the certainty of
each date made explicit — because a guided quarter is not a deadline.
A day countdown is shown only for a confirmed exact date. A guided window
shows its period, because "Q4 2026" does not mean the first of October.