Catalysts

Earnings calendar

When the companies across the AI supply chain report next. Results are where capacity, contracts and delivery dates get updated — so these are the dates most likely to move the record.

Loading dates…

Neoclouds, AI infrastructure and NVIDIA

    Across the supply chain

      Dates are exchange-scheduled events from the provider's earnings calendar, not company guidance. “Touches” lists operators linked to the reporting company by a filing — exposure, not a prediction of the result, and never investment advice.

      What has already moved the chain

      What has already moved it, and what could move it next. Every sourced change to the record, written as what happened, why it matters and what may happen next — followed by the dated events still ahead.

      (In simple terms: the things that actually move a project forward, and nothing else.)

      Lead signal

      Material signals

      20 disclosures

      The lead signal above is the most recent of the 21. The rest follow, newest first.

      • 22 Oct 2026 Medium Evidence

        Nebius Group arranges $3.5bn of financing

        What happened
        Nebius secures a $3.5bn senior secured facility from Citi.
        Why it matters
        Capital for the capacity build-out. It changes no tracked megawatt figure.
        What may happen next
        Every tracked stage on this record is complete.
        NBIS
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 7 Oct 2026 High Advanced

        Applied Digital adds 150 MW of energised critical IT

        What happened
        Applied Digital brings Polaris Forge 1 to 250 MW of live critical IT.
        Why it matters
        Building 2 was delivered in two 75 MW phases, on 1 July and 1 October. Rent commencement on Building 2 is not separately stated, so billing stays recorded at the 100 MW first building.
        What may happen next
        Every tracked stage on this record is complete.
        APLD · Polaris Forge 1
        1 source confirmed
        • Applied Digital Reports Fiscal First Quarter 2027 Results (Exhibit 99.1) Applied Digital Corporation (SEC EDGAR) · 7 Oct 2026 · Primary "On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW." Leases for approximately 1.41 GW of critical IT across five campuses, approximately $36bn over initial base terms. Expects initial operations at Polaris Forge 2 to bring delivered critical IT load across the North Dakota campuses to 300 MW by the end of calendar 2026.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 5 Oct 2026 Medium Advanced

        TeraWulf adds 500 MW of secured power

        What happened
        TeraWulf doubles contracted power at Muskie to 1 GW and brings the second phase forward to 2029.
        Why it matters
        Power at the utility, not customer capacity: no tenant is announced. The amendment still needs Kentucky PSC approval, and the first 500 MW is targeted to begin ramping in 2028.
        What may happen next
        Under construction is the next gate. No date or window has been guided for it.
        WULF · Muskie (Kentucky)
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 17 Sep 2026 Low Evidence

        CoreWeave arranges $3bn of financing

        What happened
        CoreWeave offers $3.0bn of convertible senior notes due 2033.
        Why it matters
        Financing only. The accompanying presentation restates ~1.5 GW active and ~4.2 GW contracted power, unchanged since August.
        What may happen next
        Every tracked stage on this record is complete.
        CRWV
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 27 Aug 2026 High Advanced 2 records · 1 disclosure

        IREN Limited begins earning on 40 MW of critical IT

        What happened
        IREN reports about 40 MW of AI Cloud capacity operating and $1bn of operating ARR.
        Why it matters
        The first disclosed billing figure for IREN: roughly 40 MW was earning AI Cloud revenue at 30 June, before Horizon 1 was delivered. Billing on Horizon 1 itself is still not separately disclosed.
        What may happen next
        Every tracked stage on this record is complete.
        IREN
        2 sources confirmed
        • IREN Limited annual report, fiscal year ended 30 June 2026 (Form 10-K) IREN Limited (SEC EDGAR) · 27 Aug 2026 · Primary "As of June 30, 2026, our operating AI Cloud Services capacity represented approximately 40MW." "Executed grid connection agreements ... representing approximately 5GW of total power capacity." "Horizon 2-4 is targeted for delivery in phases in calendar Q4 2026, with grace periods under the Microsoft Agreement for delivery extending from mid-Q4 2026 to the beginning of Q2 2027."
        • IREN Reports FY26 Results (Exhibit 99.1) IREN Limited (SEC EDGAR) · 27 Aug 2026 · Primary "$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 27 Aug 2026 Medium New contract

        IREN Limited signs a new customer contract

        What happened
        New multi-year AI Cloud contract with a leading frontier AI lab.
        Why it matters
        Neither the customer nor the megawatts are disclosed, so the 260 MW contracted figure stays a minimum.
        What may happen next
        Every tracked stage on this record is complete.
        IREN
        1 source confirmed
        • IREN Reports FY26 Results (Exhibit 99.1) IREN Limited (SEC EDGAR) · 27 Aug 2026 · Primary "$4bn contracted ARR for 2026 capacity; $1bn ARR operating today." Horizon 2 commissioning underway and Horizon 3-4 in late-stage construction, targeting delivery in Q4 2026. Targeting cumulative delivery of approximately 0.3GW (IT) in 2026 and 0.8GW (IT) in 2027. New multi-year AI Cloud contract with a leading frontier AI lab.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 24 Aug 2026 Low Evidence

        Nebius Group arranges $5.75bn of financing

        What happened
        Nebius closes about $5.75bn of convertible senior notes due 2030 and 2034.
        Why it matters
        Financing only. It changes no tracked megawatt figure.
        What may happen next
        Every tracked stage on this record is complete.
        NBIS
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 13 Aug 2026 High Advanced

        Microsoft accepts IREN's first 50 MW AI deployment

        What happened
        Horizon 1 — 50 MW of critical IT — delivered to and accepted by Microsoft.
        Why it matters
        The only formally accepted hyperscaler capacity across every company tracked here. Acceptance is the milestone that normally starts the revenue clock, but IREN has not separately disclosed that billing on Horizon 1 has commenced, so this site is not recorded as revenue-live.
        What may happen next
        Billing is the next gate. No date or window has been guided for it.
        IREN · Horizon 1 (Childress)
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 11 Aug 2026 High Advanced

        CoreWeave adds 500 MW of secured power

        What happened
        Contracted power reached approximately 4.2 GW, up from 3.7 GW at quarter end.
        Why it matters
        A further 500 MW of supply secured within six weeks of the quarter close. Contracted power is a total that already includes active capacity, so this widens the gap between power controlled and power energised rather than closing it.
        What may happen next
        Accepted is the next gate. No date or window has been guided for it.
        CRWV · US data centre estate
        2 sources confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 11 Aug 2026 High Advanced 2 records · 1 disclosure

        CoreWeave adds 500 MW of energised critical IT

        What happened
        Active power expanded by nearly 500 MW to reach 1.5 GW.
        Why it matters
        The largest single-quarter energisation step on the board. The previous value is derived from the company's own "expanded by nearly 500 MWs" wording rather than a separately published Q1 figure.
        What may happen next
        Accepted is the next gate. No date or window has been guided for it.
        CRWV · US data centre estate
        1 source confirmed
        • CoreWeave Reports Strong Second Quarter 2026 Results CoreWeave, Inc. · 11 Aug 2026 · Primary Expanded active power by nearly 500 MWs to reach 1.5 GW. Grew total contracted power to approximately 3.7 GW. Revenue backlog was approximately $104bn as of June 30, 2026.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 11 Aug 2026 High Evidence

        Keel Infrastructure publishes a new disclosure

        What happened
        Portfolio split disclosed: 648 MW secured, 1,513 MW planned or in development, approximately 2.2 GW total pipeline.
        Why it matters
        The 2.2 GW previously carried as secured power is a development pipeline. Secured capacity is 648 MW — under a third of the headline figure.
        What may happen next
        Every tracked stage on this record is complete.
        KEEL
        1 source confirmed
        • Keel Infrastructure Reports Second Quarter 2026 Results Keel Infrastructure · 11 Aug 2026 · Primary "With a development pipeline of 2.2 gigawatts and established grid interconnections in place." Also: "uncommitted 2027 capacity across PJM and Washington", zoning and land development approvals secured at Panther Creek, environmental permit applications progressing at Sharon, and first Vertiv modules delivered at Moses Lake. This release carries the rounded pipeline and the permitting narrative only; the itemised capacity table is in the Form 10-Q.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 11 Aug 2026 High Advanced

        TeraWulf begins earning on 102 MW of critical IT

        What happened
        Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.
        Why it matters
        One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.
        What may happen next
        Every tracked stage on this record is complete.
        WULF · Lake Mariner, New York
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 11 Aug 2026 Medium Advanced

        Keel Infrastructure passes a delivery milestone

        What happened
        Panther Creek holds 350 MW of contracted firm power with conditional land development approval; environmental permits outstanding.
        Why it matters
        A worked example of why gates are tracked independently — power and zoning have advanced while environmental approval has not, and the data centre itself is not evidenced as under construction.
        What may happen next
        Under construction is the next gate. No date or window has been guided for it.
        KEEL · Panther Creek, Pennsylvania
        1 source confirmed
        • Keel Infrastructure quarterly report (Form 10-Q) Keel Infrastructure (SEC EDGAR) · 11 Aug 2026 · Primary Current Energized Capacity 341 MW; Secured Growth Capacity 430 MW; Secured Gross Data Center Capacity 648 MW; Identified Additional Gross Data Center Capacity 1,513 MW; Total Pipeline 2,161 MW. "Secured Gross Data Center Capacity represents the total amount of gross power capacity that is subject to electric supply agreements with utilities, including both power capacity currently available on site and power capacity that utilities have agreed to deliver at a future date." Footnote: "The current energized capacity at the Panther Creek and Scrubgrass site of 60 MW and 63 MW, respectively, are not under an energy service agreement. The capacity is therefore excluded from Secured Gross Data Center Capacity."

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 7 Aug 2026 High Outlook

        Nebius Group raises its target to 5 GW

        What happened
        Year-end contracted-power target raised to 5 GW, from a measured "more than 3.5 GW".
        Why it matters
        A target, not delivered capacity. The 3.5 GW is the last explicitly measured figure; the 5 GW is an ambition for 31 December 2026 and is excluded from every current-capacity total.
        What may happen next
        Every tracked stage on this record is complete.
        NBIS
        2 sources confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 5 Aug 2026 High New contract

        APLD signs High investment-grade hyperscaler (Delta Forge 2) for 1.41 GW

        What happened
        Delta Forge 2: 210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over 15 years.
        Why it matters
        Under construction with expected delivery in H1 2028 — contracted revenue that does not begin for roughly eighteen months.
        What may happen next
        Energised is the next gate, guided for Jan–Mar 2028. A guided window is not a date.
        APLD · Delta Forge 2
        1 source confirmed
        • Applied Digital Signs 210 MW Lease at Delta Forge 2 Applied Digital Corporation · 5 Aug 2026 · Primary 210 MW lease with a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term, under construction with expected delivery in H1 2028.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 4 Aug 2026 High New contract 2 records · 1 disclosure

        WULF signs Anthropic (Justified Data Campus) for 839 MW

        What happened
        Anthropic lease at the Justified Data Campus — approximately 401 MW critical IT, 20-year initial term, approximately $19bn.
        Why it matters
        Nearly doubles disclosed contracted capacity, but initial capacity is not expected until H2 2027 and full delivery not until early 2028. Contracted is not delivered.
        What may happen next
        Power secured is the next gate. No date or window has been guided for it.
        WULF · Justified Data Campus (Anthropic)
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 29 Jul 2026 Medium Advanced

        TeraWulf passes a delivery milestone

        What happened
        FERC authorised the acquisition of Morgantown Power LLC (Docket EC26-58-000).
        Why it matters
        The first regulator-sourced record on the site, and a useful warning about headline approvals: FERC states the order covers the ownership transfer only. Data centre development, new generation, gas infrastructure, battery storage and any change to PJM participation each require separate review. Company guidance still contemplates data centre operations only in 2030.
        What may happen next
        Accepted is the next gate. No date or window has been guided for it.
        WULF · Chesapeake (Maryland)
        1 source confirmed
        • FERC Order authorising acquisition of Morgantown Power LLC — 196 FERC ¶ 61,075, Docket EC26-58-000 Federal Energy Regulatory Commission · 29 Jul 2026 · Primary Authorises Chesapeake Data LLC, a wholly owned TeraWulf subsidiary, to acquire 100% of Morgantown Power LLC from Lanyard Power Holdings LLC, finding the transfer consistent with the public interest. Morgantown Power owns four operating oil-fired generating units totalling approximately 216 MW. The authorisation covers the ownership transfer ONLY: data centre development, new generation, gas infrastructure, battery storage and changes to PJM participation each require separate review.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 15 Jul 2026 High Evidence

        Applied Digital publishes a new disclosure

        What happened
        1,410 MW of contracted critical IT across five campuses, approximately $36.2bn of contracted revenue.
        Why it matters
        The largest disclosed customer-contracted figure of any tracked company, and an exhaustive one — unlike IREN's and TeraWulf's, which are minimums. Replaces a stale 600 MW record.
        What may happen next
        Every tracked stage on this record is complete.
        APLD
        1 source confirmed
        • Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · 15 Jul 2026 · Primary 1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 1 Jun 2026 High New contract 2 records · 1 disclosure

        IREN Limited signs a customer for 260 MW

        What happened
        NVIDIA agreement for 60 MW, approximately $3.4bn over a five-year term.
        Why it matters
        Takes disclosed customer-contracted capacity to a minimum of 260 MW alongside the 200 MW Microsoft contract. Still a minimum — other contracts do not disclose megawatts.
        What may happen next
        Every tracked stage on this record is complete.
        IREN
        1 source confirmed

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      • 1 Jun 2026 High New contract

        Nebius Group signs a new customer contract

        What happened
        Meta agreement: $12bn dedicated-capacity commitment over five years.
        Why it matters
        A further $15bn may follow, relating to additional or otherwise unsold capacity, for a maximum of approximately $27bn. Only the $12bn is a commitment; the balance is conditional and is not displayed as committed revenue.
        What may happen next
        Every tracked stage on this record is complete.
        NBIS
        1 source confirmed
        • Nebius signs new AI infrastructure agreement with Meta Nebius Group N.V. · 1 Jun 2026 · Primary $12bn dedicated-capacity commitment over five years, with up to a further $15bn relating to additional or otherwise unsold capacity — a maximum possible value of approximately $27bn.

        T2C records what the document says. It does not verify the underlying event independently. How evidence is graded

      How coverage is grouped

      25 records come from 21 disclosures. 4 documents produced more than one record — a quarterly release that moves two figures at once is one disclosure, not two events.

      This is the only grouping rule applied: records resting on exactly the same document are one disclosure. T2C does not group by matching headlines, because deciding that two differently-worded announcements are "really" the same story is a judgement it cannot evidence. Corrections are never folded into the record they correct. Read the methodology

      What could move it next

      9 dated catalysts

      Dated events that could move an operational metric, with the certainty of each date made explicit — because a guided quarter is not a deadline.

      A day countdown is shown only for a confirmed exact date. A guided window shows its period, because "Q4 2026" does not mean the first of October.