GPU clouds and compute operators

Keel Infrastructure KEEL

Ex-Bitfarms portfolio with a large development pipeline, a much smaller secured base, and no announced customer lease.

Follow by RSS
—Reality Score withheld
not enough record yet
Live now
Not disclosedcritical IT, energised
Signed by customers
Not disclosedcontracted
Billing
Not discloseddisclosed as earning
Next results
Not scheduledno date announced
Sites
52 live or billing

Where Keel sits in the chain

Buys from

  • No supplier is named in a filing yet.

Sells to

  • No customer is named in a filing yet.

Each link quotes the filing that discloses it — hover for the sentence, or open KEEL on the full chain.

3 new filings not yet reviewed — the figures on this page do not reflect them yet.

  • 10 Nov 2026 8-K · Director or officer change EDGAR ↗
  • 5 Nov 2026 10-Q · Quarterly report EDGAR ↗
  • 5 Nov 2026 8-K · Results of operations EDGAR ↗

Latest on the record

  • 11 Aug 2026 Portfolio split disclosed: 648 MW secured, 1,513 MW planned or in development, approximately 2.2 GW total pipeline.
  • 11 Aug 2026 Panther Creek holds 350 MW of contracted firm power with conditional land development approval; environmental permits outstanding.

In the news

  1. Loading the latest stories…

What comes next

No guided milestone on file.

Sites

News about Keel Infrastructure

  1. Loading the latest stories…

Third-party headlines naming Keel Infrastructure or one of its disclosed suppliers or customers.

Record

Supplier passport What KEEL supplies, and how far it has actually got
Chain position AI factory Keel Infrastructure builds and operates the data centres themselves. T2C holds no record of it supplying materials, wafers, chips or photonics.
Commercial momentum Energised Has capacity switched on, with no customer disclosed against it.
Evidence confidence Unavailable Too little published record to score — see the breakdown below.

Where it sits

  1. Materials
  2. Wafers
  3. Chips + HBM
  4. Photonics
  5. AI Factory This company
  6. Accepted
  7. Revenue

T2C tracks the delivery end of the chain. The four upstream stages are not tracked for any company, so their emptiness here says nothing about Keel Infrastructure specifically.

What could break the thesis

  • No billing capacity is disclosed, so revenue timing cannot be evidenced.
  • 2 of seven delivery stages carry no disclosure: Accepted, Billing.
  • A Reality Score cannot be computed: Only 1 of 4 factors can be computed from what this company has published, covering 30% of the score's weight.

Assembled from the records, not from opinion: each item names an unresolved gate, a measured concentration, or a disclosure that does not exist.

T2C Reality Score Constructed from sourced records — not a disclosed figure
— Not enough published record to score what would be needed

Only 1 of 4 factors can be computed from what this company has published, covering 30% of the score's weight. A composite below 60% coverage is withheld rather than shown with the gaps treated as passes.

Promise delivery Not available No guided milestone has been reached yet, so there is nothing to score. 35%
Evidence quality 17 of 25 confirmed 30%
Timeline stability Not available This company has guided no dated milestone. 20%
Financing Not available Financing is not disclosed as a project milestone. 15%
Path to billing Furthest reached anywhere: Energised
  1. Building Not started
  2. Accepted Not disclosed
  3. Billing Not disclosed

A stage is marked complete when any of Keel Infrastructure's 5 tracked projects has reached it — this is the furthest the company has got anywhere, not the state of every site. Open a stage to see which sites evidence it.

Capacity truth Four different measurements
648 MW Secured Gross
Not disclosed Contracted N/A Nothing published to derive from
~244 MW Energised N/A Estimated · not disclosed
Not disclosed Billing N/A Nothing published to derive from

These are four separate disclosures on different bases, not four stages of one funnel. Secured power is measured at the utility connection; the rest are critical IT. They are never subtracted from one another.

~244 MW Estimated Energised 341 MW gross utility ÷ 1.4 = 244 MW critical IT
What is assumed

Critical IT load is taken as gross utility power divided by 1.4. Gross power is measured at the utility connection, before conversion, cooling and distribution losses. The divisor is a T2C assumption reflecting typical modern data-centre overheads, not a company figure.

Rule: Critical IT from gross utility power. Inputs are sourced; the assumption is T2C's. ↗ sec.gov

Keel Infrastructure at a glance

Every figure below is sourced
KEEL

Keel Infrastructure develops powered data-centre sites in Pennsylvania, Washington State and Québec, converting former power-generation and mining sites toward AI and HPC use.

Powered shell Reached: Energised

Where the power goes

Each row states the basis it is measured on
Power secured 648 MW GrossUnder construction not disclosedEnergised not disclosedContracted not disclosedAccepted not disclosedBilling not disclosed
Each bar is drawn to the same scale. A dashed row means the company has not published that figure — it is not zero. Where the dashed line appears, the measurement itself changes from power at the utility connection to usable capacity inside the hall, so the step down is a change of definition rather than capacity going missing.

What it owns, and what the customer brings

WHO OWNS WHAT Grid power company Building and cooling company Racks and network company Accelerators tenant Compute sold tenant
The company owns grid power, the building and the racks. The tenant supplies its own accelerators and sells its own compute.

Where it operates

5 recorded sites
4
1

A filled dot is a site with a published capacity figure; an outlined dot is a site named in filings without one. Positions are schematic, not geographic.

Capacity record

Every value with its evidence
MeasureValue and evidence
Secured powerPower capacity controlled through executed utility, interconnection, energy-service, lease or comparable arrangements. It may include capacity already operating as well as capacity awaiting development. Secured power indicates supply control, not customer demand or completed compute capacity. 648 MW ConfirmedGross ↗ sec.govas of 31 Mar 2026
Evidence · 1 source

Keel's "Secured Gross Data Center Capacity" — gross power subject to executed electric supply agreements with utilities, covering both capacity available on site today and capacity utilities have agreed to deliver at a future date. It is therefore not all available now. Replaces the 2.2 GW previously recorded as secured, which is the whole pipeline.

As of
31 Mar 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Actual
Coverage
Exhaustive total
Keel Infrastructure quarterly report (Form 10-Q) Keel Infrastructure (SEC EDGAR) · sec-filing · published 11 Aug 2026 · primary
Current Energized Capacity 341 MW; Secured Growth Capacity 430 MW; Secured Gross Data Center Capacity 648 MW; Identified Additional Gross Data Center Capacity 1,513 MW; Total Pipeline 2,161 MW. "Secured Gross Data Center Capacity represents the total amount of gross power capacity that is subject to electric supply agreements with utilities, including both power capacity currently available on site and power capacity that utilities have agreed to deliver at a future date." Footnote: "The current energized capacity at the Panther Creek and Scrubgrass site of 60 MW and 63 MW, respectively, are not under an energy service agreement. The capacity is therefore excluded from Secured Gross Data Center Capacity."
Development pipelineIdentified development opportunity that is not yet secured — sites under study, options, and applications lodged. Reported separately from secured power and never added to it. 1.51 GW ConfirmedPipelineGross ↗ sec.gov ↗ sec.govas of 31 Mar 2026
Evidence · 2 sources

"Identified Additional Gross Data Center Capacity" — not yet under an electric supply agreement. Secured 648 plus identified 1,513 gives the 2,161 MW total pipeline the company rounds to 2.2 GW.

As of
31 Mar 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Pipeline
Coverage
Exhaustive total
Keel Infrastructure quarterly report (Form 10-Q) Keel Infrastructure (SEC EDGAR) · sec-filing · published 11 Aug 2026 · primary
Current Energized Capacity 341 MW; Secured Growth Capacity 430 MW; Secured Gross Data Center Capacity 648 MW; Identified Additional Gross Data Center Capacity 1,513 MW; Total Pipeline 2,161 MW. "Secured Gross Data Center Capacity represents the total amount of gross power capacity that is subject to electric supply agreements with utilities, including both power capacity currently available on site and power capacity that utilities have agreed to deliver at a future date." Footnote: "The current energized capacity at the Panther Creek and Scrubgrass site of 60 MW and 63 MW, respectively, are not under an energy service agreement. The capacity is therefore excluded from Secured Gross Data Center Capacity."
Bitfarms / Keel Infrastructure annual report (Form 10-K) Keel Infrastructure (formerly Bitfarms) (SEC EDGAR) · sec-filing · published 1 Mar 2026 · primary
Customer-contractedCompute or capacity a paying customer has committed to under a signed contract. Demand, not supply. Frequently disclosed only for individual named contracts, in which case the site total is a disclosed minimum rather than an exhaustive figure. No announced lease
Evidence

CORRECTION: previously stored as numeric 0. No filing reports zero megawatts — the company simply has no announced lease. Stored as not disclosed with the label "No announced lease", because a zero would wrongly imply a measured figure.

Verified
Not verified
Type
Actual
Coverage
Not exhaustive — may be higher

Not disclosed by Keel Infrastructure: Under construction, Energised critical IT, Customer-accepted, Revenue live.

Verified changes

2 events
30 Jun 2026announced 11 Aug 2026

Portfolio split disclosed: 648 MW secured, 1,513 MW planned or in development, approximately 2.2 GW total pipeline.

The 2.2 GW previously carried as secured power is a development pipeline. Secured capacity is 648 MW — under a third of the headline figure.

Not disclosed648 MW
30 Jun 2026announced 11 Aug 2026

Panther Creek holds 350 MW of contracted firm power with conditional land development approval; environmental permits outstanding.

A worked example of why gates are tracked independently — power and zoning have advanced while environmental approval has not, and the data centre itself is not evidenced as under construction.

Confirmed↗ sec.gov
Not disclosedNot disclosed

About Keel Infrastructure

Last verified 15 Aug 2026

Keel Infrastructure develops powered data-centre sites in Pennsylvania, Washington State and Québec, converting former power-generation and mining sites toward AI and HPC use.

Formerly Bitfarms, Keel rebranded and redomiciled to the United States in April 2026 and now develops digital infrastructure on sites with established grid interconnections. Its portfolio is weighted toward development rather than operation: a substantially smaller amount of power is secured under executed supply agreements than the headline pipeline suggests, and no customer lease has been announced.

Company facts

Legal name
Keel Infrastructure Corp.
Ticker / exchange
KEEL · NASDAQ
Founded
Not disclosed
Headquarters
United States
Business model
Powered shell
Last verified
15 Aug 2026

Who leads it

Ben Gagnon
Chief Executive Officer
In role since 8 Jul 2024

Appointed Chief Executive Officer in July 2024, and a director of the company. Led the rebrand from Bitfarms to Keel Infrastructure and the redomiciliation to the United States.

What it sells

  • Powered data-centre site development for AI and HPC tenants
  • Sites with established grid interconnections in the PJM market
  • Bitcoin mining from earlier operations

How it makes money

Leases powered, cooled space; the tenant supplies its own accelerators where the lease says so. Earns a few million per megawatt per year rather than tens, with correspondingly lower capital cost.

Where it operates

  • United States (Pennsylvania, Washington)
  • Canada (Québec)

Operating presence as disclosed. This is not the same as future pipeline — a named location may hold nothing but secured power.

Official links

Social accounts are shown only where the link was found on a company-controlled domain. A verification badge alone is not treated as evidence.

Sources

3 documents
  • Keel Infrastructure quarterly report (Form 10-Q) Keel Infrastructure (SEC EDGAR) · sec-filing · published 11 Aug 2026 · accessed 15 Aug 2026 · primary
    Current Energized Capacity 341 MW; Secured Growth Capacity 430 MW; Secured Gross Data Center Capacity 648 MW; Identified Additional Gross Data Center Capacity 1,513 MW; Total Pipeline 2,161 MW. "Secured Gross Data Center Capacity represents the total amount of gross power capacity that is subject to electric supply agreements with utilities, including both power capacity currently available on site and power capacity that utilities have agreed to deliver at a future date." Footnote: "The current energized capacity at the Panther Creek and Scrubgrass site of 60 MW and 63 MW, respectively, are not under an energy service agreement. The capacity is therefore excluded from Secured Gross Data Center Capacity."
  • Keel Infrastructure investor presentation Keel Infrastructure · company-ir · published 11 Aug 2026 · accessed 15 Aug 2026 · primary
    Sharon 110 MW gross site capacity, of which 30 MW existing energised utility capacity and 80 MW under an energy-services agreement. Panther Creek 350 MW contracted firm power. Moses Lake 18 MW gross project capacity. Sherbrooke 96 MW conditional transfer and operation agreement.
  • Bitfarms / Keel Infrastructure annual report (Form 10-K) Keel Infrastructure (formerly Bitfarms) (SEC EDGAR) · sec-filing · published 1 Mar 2026 · accessed 15 Aug 2026 · primary