My watchlist
Updating…
Data
Checking the feed…
You
My watchlist
Display
Estimates are derived by T2C from disclosed figures. Switch them off to see only what companies have published.
Focus mode Supporting context hidden. Figures, their basis, confidence and sources are unchanged — nothing that qualifies a number is hidden.

Applied Digital

APLD · Powered shell
All values sourced Last verified 15 Aug 2026

Powered-shell developer with the largest disclosed customer-contracted critical IT figure of any tracked company, across five named campuses.

Switched on
100 MW

Critical IT load live and drawing power.

Customers have signed for
1.41 GW

Capacity under a signed customer agreement.

Delivery stage
Invoicing

The furthest gate with evidence behind it.

Next catalyst
H1 2028

Delta Forge 2 — expected delivery

T2C Reality Score Constructed from sourced records — not a disclosed figure
Not enough published record to score what would be needed

Only 2 of 4 factors can be computed from what this company has published, covering 50% of the score's weight. A composite below 60% coverage is withheld rather than shown with the gaps treated as passes.

Promise delivery Not available No guided milestone has been reached yet, so there is nothing to score. 35%
Evidence quality 17 of 19 confirmed 30%
Timeline stability 1 held 20%
Financing Not available Financing is not disclosed as a project milestone. 15%
Path to billing Furthest reached anywhere: Billing
  1. Announced Not disclosed
  2. Power Not disclosed
  3. Accepted Not started

A stage is marked complete when any of Applied Digital's 5 tracked projects has reached it — this is the furthest the company has got anywhere, not the state of every site. Open a stage to see which sites evidence it.

Capacity truth Four different measurements
2.15 GW Secured Gross
1.41 GW Contracted Critical IT
100 MW Energised Critical IT
100 MW Billing Critical IT

These are four separate disclosures on different bases, not four stages of one funnel. Secured power is measured at the utility connection; the rest are critical IT. They are never subtracted from one another.

Revenue calculator What billing capacity implies, and what it would be worth

The megawatts and the revenue rate come from what Applied Digital has published. The multiple does not — it is an opinion, and it is the input that moves the answer most. Nothing here is a price target.

Every option above is measured as critical IT, the same basis the revenue rate is derived on. Secured power is deliberately absent: it is gross power at the utility connection, and applying a per-MW contract rate to it would price megawatts that cannot be sold as compute.

MW
Disclosed by the company
$ m
Derived from APLD’s own contracts

capacity-weighted mean of 5 disclosed contracts (1410 MW total) = $1.71m per MW per year

×
An opinion — not a disclosure
m
Fetching from the provider…
Run-rate revenue
Implied enterprise value
Enterprise value per share
Against the live price
How much of that is the multiple
EV / revenueEnterprise value Per sharevs price

Applied Digital at a glance

Every figure below is sourced
APLD

Applied Digital builds large data-centre campuses and leases them to hyperscale customers on long initial terms, with the tenant supplying its own compute hardware.

Powered shell Reached: Invoicing 5% of controlled power switched on

How far it has actually got

Select a step for its evidence

Where the power goes

Power controlled 2.15 GW Gross measurement changes to Critical ITBeing built 1.50 GW Critical ITSwitched on 100 MW Critical ITCustomers signed for 1.41 GW Critical ITDelivered and accepted not disclosedGenerating revenue 100 MW Critical IT
Each bar is drawn to the same scale. A dashed row means the company has not published that figure — it is not zero. Where the dashed line appears, the measurement itself changes from power at the utility connection to usable capacity inside the hall, so the step down is a change of definition rather than capacity going missing.

What it owns, and what the customer brings

WHO OWNS WHAT Grid power company Building and cooling company Racks and network company Accelerators tenant Compute sold tenant
The company owns grid power, the building and the racks. The tenant supplies its own accelerators and sells its own compute.

Where it operates

5 recorded sites
5

A filled dot is a site with a published capacity figure; an outlined dot is a site named in filings without one. Positions are schematic, not geographic.

Capacity record

Every value with its evidence
MeasureValue and evidence
Secured powerPower capacity controlled through executed utility, interconnection, energy-service, lease or comparable arrangements. It may include capacity already operating as well as capacity awaiting development. Secured power indicates supply control, not customer demand or completed compute capacity. 2.15 GW ConfirmedGross ↗ sec.govas of 31 May 2026
Evidence · 1 source

Approximately 2.15 GW of gross grid-connected utility power. Gross basis — not comparable with the 1,410 MW critical IT figure.

As of
31 May 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Actual
Coverage
Exhaustive total
Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · sec-filing · published 15 Jul 2026 · primary
1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.
Development pipelineIdentified development opportunity that is not yet secured — sites under study, options, and applications lodged. Reported separately from secured power and never added to it. Not disclosed Not disclosed
Customer-contractedCompute or capacity a paying customer has committed to under a signed contract. Demand, not supply. Frequently disclosed only for individual named contracts, in which case the site total is a disclosed minimum rather than an exhaustive figure. 1.41 GW ConfirmedCritical IT ↗ sec.govas of 31 May 2026
Evidence · 1 source

Contracted critical IT across five campuses, with approximately $36.2bn of contracted revenue over the initial base terms. Replaces the stale 600 MW record.

As of
31 May 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Exhaustive total
Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · sec-filing · published 15 Jul 2026 · primary
1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.
Under constructionCapacity with physical construction under way. Capital committed, no revenue from it yet. 1.50 GW ConfirmedCritical IT ↗ sec.govas of 31 May 2026
Evidence · 1 source

Approximately 1.5 GW operating OR under construction across the five campuses — the company reports the two together, so this is not a pure construction figure and includes the 100 MW already operational.

As of
31 May 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Not exhaustive — may be higher
Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · sec-filing · published 15 Jul 2026 · primary
1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.
Energised critical ITCritical IT load live and drawing power. Often described by companies as "active" or "operational" capacity. It does not by itself mean a customer is paying for it. 100 MW ConfirmedCritical IT ↗ sec.govas of 31 May 2026
Evidence · 1 source

Approximately 100 MW operational and revenue-generating.

As of
31 May 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Exhaustive total
Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · sec-filing · published 15 Jul 2026 · primary
1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.
Customer-acceptedCapacity formally accepted under the relevant customer agreement. Acceptance may trigger billing or revenue recognition, but the commercial effect is contract-specific and must be separately evidenced. Not disclosed Not disclosed
Revenue liveCapacity for which the company has explicitly disclosed that billing, rent commencement or revenue generation has begun. Billing, GAAP revenue recognition and cash receipt are not assumed to occur simultaneously. 100 MW ConfirmedCritical IT ↗ sec.govas of 31 May 2026
Evidence · 1 source

Explicitly described as operational and revenue-generating.

As of
31 May 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Exhaustive total
Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · sec-filing · published 15 Jul 2026 · primary
1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.

Projects and gates

5 recorded
Gates advance independently. Zoning can be granted while environmental approval, financing and interconnection all remain outstanding — a single stage label would hide that.

Polaris Forge 1

United States
400 MW Critical ITConfirmed

400 MW leased to CoreWeave, approximately $11bn over a 15-year initial term.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started Complete · 1 source
  11. Utility energised Not disclosed
  12. Critical IT energised In progress · 1 source
  13. Customer contracted Complete · 1 source
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Complete · 1 source

Polaris Forge 2

United States
200 MW Critical ITConfirmed

200 MW leased to an investment-grade hyperscaler, approximately $5bn over a 15-year initial term.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started In progress · 1 source
  11. Utility energised Not disclosed
  12. Critical IT energised Not disclosed
  13. Customer contracted Complete · 1 source
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Not disclosed

Polaris Forge 3

United States
300 MW Critical ITConfirmed

300 MW leased to a high investment-grade hyperscaler, approximately $7.5bn over a 15-year initial term.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started In progress · 1 source
  11. Utility energised Not disclosed
  12. Critical IT energised Not disclosed
  13. Customer contracted Complete · 1 source
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Not disclosed

Delta Forge 1

United States
300 MW Critical ITConfirmed

300 MW leased to a high investment-grade hyperscaler, approximately $7.5bn over a 15-year initial term.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started In progress · 1 source
  11. Utility energised Not disclosed
  12. Critical IT energised Not disclosed
  13. Customer contracted Complete · 1 source
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Not disclosed

Delta Forge 2

United States
210 MW Critical ITConfirmed

210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term. Under construction, with initial operations anticipated in Q1 2028.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started Complete · 1 source
  11. Utility energised Not disclosed
  12. Critical IT energised Not started
  13. Customer contracted Complete · 1 source 5 Aug 2026
  14. Customer accepted Not started
  15. Billing / revenue commenced Not disclosed
Critical IT energised
Target Q1 2028 Actual Not disclosed
Not yet reached
"Initial operations are anticipated to commence in Q1 2028." The release is more precise than the H1 2028 previously recorded here.
↗ ir.applieddigital.comguided 5 Aug 2026
Contract X-ray 5 disclosed agreements
CoreWeave (Polaris Forge 1) 400 MW
Firm
$11bn

15-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

15-year initial term.

Investment-grade hyperscaler (Polaris Forge 2) 200 MW
Firm
$5bn

15-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

15-year initial term. Customer not named by the company.

High investment-grade hyperscaler (Polaris Forge 3) 300 MW
Firm
$7.5bn

15-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

15-year initial term. Customer not named by the company.

High investment-grade hyperscaler (Delta Forge 1) 300 MW
Firm
$7.5bn

15-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

15-year initial term. Customer not named by the company.

High investment-grade hyperscaler (Delta Forge 2) 210 MW
Firm
$5.2bn

15-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

15-year initial term. Under construction, expected delivery H1 2028.

Committed value and conditional maximum are shown apart and never added. Where a company discloses a ceiling — "up to" — the difference depends on events that have not happened.

Contract detail

Every disclosed field
Scroll sideways for all columns →
CustomerMWTerm ValueDeliveredTerms
CoreWeave (Polaris Forge 1) 400 MWCritical IT 15 yr $11bn Not disclosed 15-year initial term.↗ sec.gov
Investment-grade hyperscaler (Polaris Forge 2) 200 MWCritical IT 15 yr $5bn Not disclosed 15-year initial term. Customer not named by the company.↗ sec.gov
High investment-grade hyperscaler (Polaris Forge 3) 300 MWCritical IT 15 yr $7.5bn Not disclosed 15-year initial term. Customer not named by the company.↗ sec.gov
High investment-grade hyperscaler (Delta Forge 1) 300 MWCritical IT 15 yr $7.5bn Not disclosed 15-year initial term. Customer not named by the company.↗ sec.gov
High investment-grade hyperscaler (Delta Forge 2) 210 MWCritical IT 15 yr $5.2bn Not disclosed 15-year initial term. Under construction, expected delivery H1 2028.↗ ir.applieddigital.com

Verified changes

2 events
5 Aug 2026announced 5 Aug 2026

Delta Forge 2: 210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over 15 years.

Under construction with expected delivery in H1 2028 — contracted revenue that does not begin for roughly eighteen months.

1.20 GW1.41 GW
31 May 2026announced 15 Jul 2026

1,410 MW of contracted critical IT across five campuses, approximately $36.2bn of contracted revenue.

The largest disclosed customer-contracted figure of any tracked company, and an exhaustive one — unlike IREN's and TeraWulf's, which are minimums. Replaces a stale 600 MW record.

Confirmed↗ sec.gov
600 MW1.41 GW

Upcoming catalysts

1
APLD

Delta Forge 2 — expected delivery

210 MW under construction for a high investment-grade hyperscaler, approximately $5.2bn over 15 years. Guided to H1 2028.

Make your call

Private to this browser

Write down what you expect Applied Digital to deliver, and by when. T2C scores it later against the same evidenced gates it uses everywhere else — not against the share price.

Stored in this browser only. Clearing your browser data deletes it, and T2C never receives it — there is nowhere for it to be sent.

About Applied Digital

Last verified 15 Aug 2026

Applied Digital builds large data-centre campuses and leases them to hyperscale customers on long initial terms, with the tenant supplying its own compute hardware.

Applied Digital develops purpose-built AI data centres across five named campuses and leases them under long initial terms. It has the largest disclosed customer-contracted critical IT figure of any company tracked here, and unlike several peers it publishes an exhaustive total rather than a set of individual deals.

Company facts

Legal name
Applied Digital Corporation
Ticker / exchange
APLD · NASDAQ
Founded
Not disclosed
Headquarters
Dallas, Texas, United States
Business model
Powered shell
Last verified
15 Aug 2026

Who leads it

Wes Cummins
Chairman and Chief Executive Officer

Chairman and Chief Executive Officer of Applied Digital, with a background as a technology investor.

↗ ir.applieddigital.comverified 15 Aug 2026

What it sells

  • Long-term data-centre leases to hyperscale customers
  • Purpose-built AI campuses developed and operated in-house
  • Cloud services from earlier operations

How it makes money

Leases powered, cooled space; the tenant supplies its own accelerators where the lease says so. Earns a few million per megawatt per year rather than tens, with correspondingly lower capital cost.

Where it operates

  • United States (North Dakota, Texas)

Operating presence as disclosed. This is not the same as future pipeline — a named location may hold nothing but secured power.

Publicly disclosed customers

  • CoreWeave

Only customers the company has named publicly. Several tracked companies describe counterparties only as "investment-grade hyperscaler", and those are not guessed at here.

Official links

Social accounts are shown only where the link was found on a company-controlled domain. A verification badge alone is not treated as evidence.

Sources

2 documents
  • Applied Digital Signs 210 MW Lease at Delta Forge 2 Applied Digital Corporation · company-ir · published 5 Aug 2026 · accessed 15 Aug 2026 · primary
    210 MW lease with a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term, under construction with expected delivery in H1 2028.
  • Applied Digital Corporation annual report, fiscal year ended 31 May 2026 Applied Digital Corporation (SEC EDGAR) · sec-filing · published 15 Jul 2026 · accessed 15 Aug 2026 · primary
    1,410 MW of contracted critical IT capacity across five campuses, approximately $36.2bn of contracted revenue over initial base terms, approximately 2.15 GW of gross grid-connected utility power, approximately 100 MW operational and revenue-generating, and approximately 1.5 GW operating or under construction.