Third-party headlines naming TeraWulf or one of its disclosed suppliers or customers.
Record
Supplier passportWhat WULF supplies, and how far it has actually got
Chain positionAI factoryTeraWulf builds and operates the data centres themselves. T2C holds no record of it supplying materials, wafers, chips or photonics.
Commercial momentumBillingHas disclosed capacity that is billing.
Evidence confidenceUnavailableToo little published record to score — see the breakdown below.
Where it sits
—Materials
—Wafers
—Chips + HBM
○Photonics
●AI FactoryThis company
○Accepted
○Revenue
T2C tracks the delivery end of the chain. The four upstream stages are not
tracked for any company, so their emptiness here says nothing about
TeraWulf specifically.
What could break the thesis
⚠ 100% of disclosed contracted capacity sits with Anthropic (Justified Data Campus).
⚠ A Reality Score cannot be computed: Only 2 of 4 factors can be computed from what this company has published, covering 50% of the score's weight.
Assembled from the records, not from opinion: each item names an unresolved gate,
a measured concentration, or a disclosure that does not exist.
T2C Reality ScoreConstructed from sourced records — not a disclosed figure
Only 2 of 4 factors can be computed from what this company has published, covering 50% of the score's weight. A composite below 60% coverage is withheld rather than shown with the gaps treated as passes.
Promise deliveryNot availableNo guided milestone has been reached yet, so there is nothing to score.35%
Evidence quality17 of 24 confirmed30%
Timeline stability8 held20%
FinancingNot availableFinancing is not disclosed as a project milestone.15%
A stage is marked complete when any of TeraWulf's
4 tracked projects has reached it —
this is the furthest the company has got anywhere, not the state of every site.
Open a stage to see which sites evidence it.
Capacity truthFour different measurements
⌁Not disclosedSecuredN/ANothing published to derive from
§839 MWContractedCritical IT
▣102 MWEnergisedCritical IT
$102 MWBillingCritical IT
These are four separate disclosures on different bases, not four stages of one
funnel. Secured power is measured at the utility connection; the rest are critical IT. They are
never subtracted from one another.
TeraWulf at a glance
Every figure below is sourced
TeraWulf develops powered data-centre campuses and leases them to compute tenants under long-term agreements, rather than owning the accelerators itself.
◇Powered shell●Reached: Billing
Where the power goes
Each row states the basis it is measured on
Each bar is drawn to the same scale. A dashed row means the company has not published
that figure — it is not zero. Where the dashed line appears, the measurement itself changes from
power at the utility connection to usable capacity inside the hall, so the step down is a change
of definition rather than capacity going missing.
What it owns, and what the customer brings
The company owns grid power, the building and the racks. The tenant supplies its own accelerators and sells its own compute.
Where it operates
4 recorded sites
🇺🇸4
A filled dot is a site with a published capacity figure; an outlined dot is a
site named in filings without one. Positions are schematic, not geographic.
Capacity record
Every value with its evidence
Measure
Value and evidence
Customer-contractedCompute or capacity a paying customer has committed to under a signed contract. Demand, not supply. Frequently disclosed only for individual named contracts, in which case the site total is a disclosed minimum rather than an exhaustive figure.
Lake Mariner 438 MW (102 MW revenue-generating plus 336 MW under construction) and Anthropic/Justified approximately 401 MW. A disclosed minimum — the company has not published an updated exhaustive contracted total.
Approximately 401 MW of critical IT capacity under a 20-year initial lease term, approximately $19bn of contracted revenue over the initial term. Initial capacity expected in H2 2027 with full delivery expected in early 2028. Sale of TeraWulf's 50.1% interest in the Abernathy joint venture.
Under constructionCapacity with physical construction under way. Capital committed, no revenue from it yet.
Lake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.
Energised critical ITCritical IT load live and drawing power. Often described by companies as "active" or "operational" capacity. It does not by itself mean a customer is paying for it.
Lake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.
Revenue liveCapacity for which the company has explicitly disclosed that billing, rent commencement or revenue generation has begun. Billing, GAAP revenue recognition and cash receipt are not assumed to occur simultaneously.
Muskie: up to 1 GW of contracted electric service. Chesapeake: approximately 210 MW of operational generation with potential future campus scale of up to 1 GW.
Muskie: up to 1 GW of contracted electric service. Chesapeake: approximately 210 MW of operational generation with potential future campus scale of up to 1 GW.
Contract X-ray1 disclosed agreement
Anthropic (Justified Data Campus)401 MW
Firm
$19bn
20-year term, committed.
Optional
None disclosed
The company has disclosed no conditional upside on this agreement.
Delivered
None yet
Contracted is not delivered. Nothing has been accepted under this agreement yet.
20-year initial lease term. Initial capacity expected H2 2027, full delivery expected early 2028.
Committed value and conditional maximum are shown apart and never added. Where a
company discloses a ceiling — "up to" — the difference depends on events that have not happened.
Contract detail
Every disclosed field
Scroll sideways for all columns →
Customer
MW
Term
Value
Delivered
Terms
Anthropic (Justified Data Campus)
401 MWCritical IT
20 yr
$19bn
Not disclosed
20-year initial lease term. Initial capacity expected H2 2027, full delivery expected early 2028.↗ investors.terawulf.com
Verified changes
6 events
23 Oct 2026announced 23 Oct 2026
TeraWulf raises its revolving credit facility from $250m to about $400m.
Financing only. It changes no tracked megawatt figure.
TeraWulf doubles contracted power at Muskie to 1 GW and brings the second phase forward to 2029.
Power at the utility, not customer capacity: no tenant is announced. The amendment still needs Kentucky PSC approval, and the first 500 MW is targeted to begin ramping in 2028.
Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.
One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.
Anthropic lease at the Justified Data Campus — approximately 401 MW critical IT, 20-year initial term, approximately $19bn.
Nearly doubles disclosed contracted capacity, but initial capacity is not expected until H2 2027 and full delivery not until early 2028. Contracted is not delivered.
Sale of TeraWulf's 50.1% interest in the Abernathy joint venture to Fluidstack.
Capacity disposed of must leave current owned totals. This is one reason the February 2.2 GW pipeline figure is retained as historical rather than carried forward as a current value.
FERC authorised the acquisition of Morgantown Power LLC (Docket EC26-58-000).
The first regulator-sourced record on the site, and a useful warning about headline approvals: FERC states the order covers the ownership transfer only. Data centre development, new generation, gas infrastructure, battery storage and any change to PJM participation each require separate review. Company guidance still contemplates data centre operations only in 2030.
First tranche of the approximately 401 MW Anthropic lease. Company guidance is H2 2027 — a half-year window, not a date. Would be the first energisation at the Justified campus.
Completion of the approximately 401 MW lease. Guided to early 2028. Full delivery would take TeraWulf's contracted capacity toward acceptance and, contract terms permitting, revenue.
Utility power, not a customer delivery: no tenant has been announced for Muskie. The second 500 MW phase is guided for 2029, subject to Kentucky PSC approval.
TeraWulf develops powered data-centre campuses and leases them to compute tenants under long-term agreements, rather than owning the accelerators itself.
TeraWulf converts sites with strong power positions into data-centre capacity and leases that capacity to customers on long terms. Its Lake Mariner campus in New York is generating revenue, and a very large lease at its Justified campus does not begin delivering until the second half of 2027 — the gap between contracted and delivered is the central question for the company.
Company facts
Legal name
TeraWulf Inc.
Ticker / exchange
WULF · NASDAQ
Founded
2021
Headquarters
Easton, Maryland, United States
Business model
Powered shell
Last verified
15 Aug 2026
Who leads it
Paul B. Prager
Co-Founder, Chairman and Chief Executive Officer
In role since 1 Feb 2021
Co-founder of TeraWulf, serving as Chairman and Chief Executive Officer since February 2021. Previously founded and led Beowulf Electricity & Data.
Powered campus development on owned and acquired sites
Power generation assets supporting those campuses
How it makes money
Leases powered, cooled space; the tenant supplies its own accelerators where the lease says so. Earns a few million per megawatt per year rather than tens, with correspondingly lower capital cost.
Where it operates
United States (New York, Maryland, Kentucky)
Operating presence as disclosed. This is not the same as future pipeline —
a named location may hold nothing but secured power.
Publicly disclosed customers
Anthropic
Only customers the company has named publicly. Several tracked companies
describe counterparties only as "investment-grade hyperscaler", and those are not guessed at here.
Amended and restated electric service agreement with Kentucky Power increasing contracted power capacity at Muskie from 500 MW to 1 GW; second 500 MW phase advanced from 2030 to 2029, subject to Kentucky PSC approval. First 500 MW phase remains targeted to begin ramping in 2028.
Approximately 401 MW of critical IT capacity under a 20-year initial lease term, approximately $19bn of contracted revenue over the initial term. Initial capacity expected in H2 2027 with full delivery expected in early 2028. Sale of TeraWulf's 50.1% interest in the Abernathy joint venture.
Muskie: up to 1 GW of contracted electric service. Chesapeake: approximately 210 MW of operational generation with potential future campus scale of up to 1 GW.