My watchlist
Updating…
Data
Checking the feed…
You
My watchlist
Display
Estimates are derived by T2C from disclosed figures. Switch them off to see only what companies have published.
Focus mode Supporting context hidden. Figures, their basis, confidence and sources are unchanged — nothing that qualifies a number is hidden.

TeraWulf

WULF · Powered shell
All values sourced Last verified 15 Aug 2026

Powered-shell landlord converting legacy sites to HPC leasing, with a very large Anthropic lease that does not begin delivering until H2 2027.

Switched on
102 MW

Critical IT load live and drawing power.

Customers have signed for
839 MWDisclosed minimum

Capacity under a signed customer agreement.

Delivery stage
Invoicing

The furthest gate with evidence behind it.

Next catalyst
H2 2027

Anthropic / Justified — initial capacity delivery

T2C Reality Score Constructed from sourced records — not a disclosed figure
Not enough published record to score what would be needed

Only 2 of 4 factors can be computed from what this company has published, covering 50% of the score's weight. A composite below 60% coverage is withheld rather than shown with the gaps treated as passes.

Promise delivery Not available No guided milestone has been reached yet, so there is nothing to score. 35%
Evidence quality 15 of 22 confirmed 30%
Timeline stability 7 held 20%
Financing Not available Financing is not disclosed as a project milestone. 15%
Path to billing Furthest reached anywhere: Billing
  1. Accepted Not started

A stage is marked complete when any of TeraWulf's 4 tracked projects has reached it — this is the furthest the company has got anywhere, not the state of every site. Open a stage to see which sites evidence it.

Capacity truth Four different measurements
Not disclosed Secured N/A Nothing published to derive from
839 MW Contracted Critical IT
102 MW Energised Critical IT
102 MW Billing Critical IT

These are four separate disclosures on different bases, not four stages of one funnel. Secured power is measured at the utility connection; the rest are critical IT. They are never subtracted from one another.

Revenue calculator What billing capacity implies, and what it would be worth

The megawatts and the revenue rate come from what TeraWulf has published. The multiple does not — it is an opinion, and it is the input that moves the answer most. Nothing here is a price target.

Every option above is measured as critical IT, the same basis the revenue rate is derived on. Secured power is deliberately absent: it is gross power at the utility connection, and applying a per-MW contract rate to it would price megawatts that cannot be sold as compute.

MW
Disclosed by the company
$ m
Derived from WULF’s own contracts

Anthropic (Justified Data Campus): $19bn ÷ 401 MW ÷ 20 years = $2.37m per MW per year

×
An opinion — not a disclosure
m
Fetching from the provider…
Run-rate revenue
Implied enterprise value
Enterprise value per share
Against the live price
How much of that is the multiple
EV / revenueEnterprise value Per sharevs price

TeraWulf at a glance

Every figure below is sourced
WULF

TeraWulf develops powered data-centre campuses and leases them to compute tenants under long-term agreements, rather than owning the accelerators itself.

Powered shell Reached: Invoicing

How far it has actually got

Select a step for its evidence

Where the power goes

Power controlled not disclosedBeing built 336 MW Critical ITSwitched on 102 MW Critical ITCustomers signed for ≥839 MW Critical ITDelivered and accepted not disclosedGenerating revenue 102 MW Critical IT
Each bar is drawn to the same scale. A dashed row means the company has not published that figure — it is not zero. Where the dashed line appears, the measurement itself changes from power at the utility connection to usable capacity inside the hall, so the step down is a change of definition rather than capacity going missing.

What it owns, and what the customer brings

WHO OWNS WHAT Grid power company Building and cooling company Racks and network company Accelerators tenant Compute sold tenant
The company owns grid power, the building and the racks. The tenant supplies its own accelerators and sells its own compute.

Where it operates

4 recorded sites
4

A filled dot is a site with a published capacity figure; an outlined dot is a site named in filings without one. Positions are schematic, not geographic.

Capacity record

Every value with its evidence
MeasureValue and evidence
Secured powerPower capacity controlled through executed utility, interconnection, energy-service, lease or comparable arrangements. It may include capacity already operating as well as capacity awaiting development. Secured power indicates supply control, not customer demand or completed compute capacity. Not disclosed Not disclosed
Evidence

The 2.2 GW owned pipeline and 642.5 MW contracted figures were February 2026 disclosures and are retained as historical events rather than current values. No comparable current secured-power total on a single basis has been located.

Verified
Not verified
Type
Actual
Coverage
Not exhaustive — may be higher
Development pipelineIdentified development opportunity that is not yet secured — sites under study, options, and applications lodged. Reported separately from secured power and never added to it. Not disclosed Not disclosed
Customer-contractedCompute or capacity a paying customer has committed to under a signed contract. Demand, not supply. Frequently disclosed only for individual named contracts, in which case the site total is a disclosed minimum rather than an exhaustive figure. ≥839 MW ConfirmedDisclosed minimumCritical IT ↗ investors.terawulf.com ↗ investors.terawulf.comas of 4 Aug 2026
Evidence · 2 sources

Lake Mariner 438 MW (102 MW revenue-generating plus 336 MW under construction) and Anthropic/Justified approximately 401 MW. A disclosed minimum — the company has not published an updated exhaustive contracted total.

As of
4 Aug 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Disclosed minimum
Coverage
Not exhaustive — may be higher
TeraWulf Reports Second Quarter 2026 Results TeraWulf Inc. · company-ir · published 11 Aug 2026 · primary
Lake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.
TeraWulf Announces Anthropic Lease at Justified Data Campus and Sale of Majority Interest in Abernathy Joint Venture to Fluidstack TeraWulf Inc. · company-ir · published 4 Aug 2026 · primary
Approximately 401 MW of critical IT capacity under a 20-year initial lease term, approximately $19bn of contracted revenue over the initial term. Initial capacity expected in H2 2027 with full delivery expected in early 2028. Sale of TeraWulf's 50.1% interest in the Abernathy joint venture.
Under constructionCapacity with physical construction under way. Capital committed, no revenue from it yet. 336 MW ConfirmedCritical IT ↗ investors.terawulf.comas of 30 Jun 2026
Evidence · 1 source

Additional Lake Mariner critical IT under construction.

As of
30 Jun 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Not exhaustive — may be higher
TeraWulf Reports Second Quarter 2026 Results TeraWulf Inc. · company-ir · published 11 Aug 2026 · primary
Lake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.
Energised critical ITCritical IT load live and drawing power. Often described by companies as "active" or "operational" capacity. It does not by itself mean a customer is paying for it. 102 MW ConfirmedCritical IT ↗ investors.terawulf.comas of 30 Jun 2026
Evidence · 1 source

Lake Mariner revenue-generating critical IT capacity.

As of
30 Jun 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Exhaustive total
TeraWulf Reports Second Quarter 2026 Results TeraWulf Inc. · company-ir · published 11 Aug 2026 · primary
Lake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.
Customer-acceptedCapacity formally accepted under the relevant customer agreement. Acceptance may trigger billing or revenue recognition, but the commercial effect is contract-specific and must be separately evidenced. Not disclosed Not disclosed
Revenue liveCapacity for which the company has explicitly disclosed that billing, rent commencement or revenue generation has begun. Billing, GAAP revenue recognition and cash receipt are not assumed to occur simultaneously. 102 MW ConfirmedCritical IT ↗ investors.terawulf.comas of 30 Jun 2026
Evidence · 1 source

Explicitly described as revenue-generating, which is the disclosure needed to record revenue-live.

As of
30 Jun 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Exhaustive total
TeraWulf Reports Second Quarter 2026 Results TeraWulf Inc. · company-ir · published 11 Aug 2026 · primary
Lake Mariner: 102 MW of revenue-generating critical IT capacity, with a further 336 MW of critical IT under construction.

Superseded disclosures

Retained and dated, not deleted
Development pipelineHistorical disclosure — superseded 2.20 GW ReportedPipelineGross ↗ investors.terawulf.comas of 1 Feb 2026
Evidence · 1 source

February 2026 owned-pipeline disclosure. Retained as historical; superseded by later portfolio changes including the Abernathy disposal.

As of
1 Feb 2026
Verified
15 Aug 2026
Basis
Gross utility power
Type
Pipeline
Coverage
Not exhaustive — may be higher
TeraWulf Expands Digital and Power Infrastructure Portfolio with Strategic Acquisitions in Kentucky and Maryland TeraWulf Inc. · company-ir · published 1 Feb 2026 · primary
Muskie: up to 1 GW of contracted electric service. Chesapeake: approximately 210 MW of operational generation with potential future campus scale of up to 1 GW.
Customer-contractedHistorical disclosure — superseded 642.5 MW ReportedCritical IT ↗ investors.terawulf.comas of 1 Feb 2026
Evidence · 1 source

February 2026 contracted-capacity disclosure, superseded by the August 2026 figures above.

As of
1 Feb 2026
Verified
15 Aug 2026
Basis
Critical IT load
Type
Actual
Coverage
Not exhaustive — may be higher
TeraWulf Expands Digital and Power Infrastructure Portfolio with Strategic Acquisitions in Kentucky and Maryland TeraWulf Inc. · company-ir · published 1 Feb 2026 · primary
Muskie: up to 1 GW of contracted electric service. Chesapeake: approximately 210 MW of operational generation with potential future campus scale of up to 1 GW.

Projects and gates

4 recorded
Gates advance independently. Zoning can be granted while environmental approval, financing and interconnection all remain outstanding — a single stage label would hide that.

Lake Mariner, New York

United States
438 MW Critical ITConfirmed

102 MW revenue-generating critical IT plus 336 MW additional critical IT under construction across CB-4 and CB-5. CB-3 delivery completed in early July 2026.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started In progress · 1 source
  11. Utility energised Complete · 1 source
  12. Critical IT energised Complete · 1 source 30 Jun 2026
  13. Customer contracted Complete · 1 source
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Complete · 1 source 30 Jun 2026
Critical IT energisedCB-5
Target Q1 2027 Actual Not disclosed
Not yet reached
CB-5: "targeted to begin phased delivery in early 2027". Recorded as Q1 as the narrowest defensible reading of "early".
↗ investors.terawulf.comguided 11 Aug 2026
Customer acceptedCB-3
Target 31 Jul 2026 Actual Not disclosed
Not yet reached
"Completed delivery of CB-3 in early July" 2026. Already delivered; recorded for the record, not as an outstanding target.
↗ investors.terawulf.comguided 11 Aug 2026
Billing / revenue commencedCB-4
Target H2 2026 Actual Not disclosed
Not yet reached
CB-4: "phased delivery and rent commencement expected during the second half of 2026".
↗ investors.terawulf.comguided 11 Aug 2026

Justified Data Campus (Anthropic)

United States
401 MW Critical ITConfirmed

Approximately 401 MW critical IT on a 20-year initial lease, approximately $19bn contracted revenue over the initial term. Initial capacity expected H2 2027, full delivery early 2028.

  1. Site control Not disclosed
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started Not disclosed
  11. Utility energised Not disclosed
  12. Critical IT energised Not started
  13. Customer contracted Complete · 1 source 4 Aug 2026
  14. Customer accepted Not started
  15. Billing / revenue commenced Not started
Critical IT energised
Target H2 2027 Actual Not disclosed
Not yet reached
"Initial delivery expected in the second half of 2027".
Customer accepted
Target H1 2028 Actual Not disclosed
Not yet reached
"Full delivery expected in early 2028". Recorded as H1 2028 — "early" is not a quarter.

Muskie (Kentucky)

United States
1 GW GrossPotentialConfirmed

Up to 1 GW of contracted electric service via Kentucky Power Company. This is power availability at the utility, not customer-contracted critical IT, and is excluded from contracted-capacity totals.

  1. Site control Complete · 1 source
  2. Utility agreement Complete · 1 source
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval Not disclosed
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started Not started
  11. Utility energised Not disclosed
  12. Critical IT energised Not disclosed
  13. Customer contracted Not disclosed
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Not disclosed
Critical IT energised
Target Q4 2028 Actual Not disclosed
Not yet reached
"Initial service expected in the fourth quarter of 2028".
↗ investors.terawulf.comguided 11 Aug 2026

Chesapeake (Maryland)

United States
210 MW GrossConfirmed

Approximately 210 MW operational generation at the Morgantown Generating Station. A further campus scale of up to 1 GW is potential only and is not current critical IT.

  1. Site control Conditional · 2 sources 29 Jul 2026
  2. Utility agreement Not disclosed
  3. Interconnection approved Not disclosed
  4. Zoning approved Not disclosed
  5. Regulatory approval In progress · 1 source 29 Jul 2026
  6. Environmental approval Not disclosed
  7. Building permits Not disclosed
  8. Financing committed Not disclosed
  9. Long-lead equipment ordered Not disclosed
  10. Construction started Not disclosed
  11. Utility energised Complete · 2 sources
  12. Critical IT energised Not started
  13. Customer contracted Not disclosed
  14. Customer accepted Not disclosed
  15. Billing / revenue commenced Not disclosed
Critical IT energised
Target 2030 Actual Not disclosed
Not yet reached
"Initial data center operations currently contemplated for 2030" — contemplated, not committed, and four years out.
↗ investors.terawulf.comguided 11 Aug 2026
Contract X-ray 1 disclosed agreement
Anthropic (Justified Data Campus) 401 MW
Firm
$19bn

20-year term, committed.

Optional
None disclosed

The company has disclosed no conditional upside on this agreement.

Delivered
None yet

Contracted is not delivered. Nothing has been accepted under this agreement yet.

20-year initial lease term. Initial capacity expected H2 2027, full delivery expected early 2028.

Committed value and conditional maximum are shown apart and never added. Where a company discloses a ceiling — "up to" — the difference depends on events that have not happened.

Contract detail

Every disclosed field
Scroll sideways for all columns →
CustomerMWTerm ValueDeliveredTerms
Anthropic (Justified Data Campus) 401 MWCritical IT 20 yr $19bn Not disclosed 20-year initial lease term. Initial capacity expected H2 2027, full delivery expected early 2028.↗ investors.terawulf.com

Verified changes

4 events
30 Jun 2026announced 11 Aug 2026

Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.

One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.

Not disclosed102 MW
4 Aug 2026announced 4 Aug 2026

Anthropic lease at the Justified Data Campus — approximately 401 MW critical IT, 20-year initial term, approximately $19bn.

Nearly doubles disclosed contracted capacity, but initial capacity is not expected until H2 2027 and full delivery not until early 2028. Contracted is not delivered.

438 MW839 MW
4 Aug 2026announced 4 Aug 2026

Sale of TeraWulf's 50.1% interest in the Abernathy joint venture to Fluidstack.

Capacity disposed of must leave current owned totals. This is one reason the February 2.2 GW pipeline figure is retained as historical rather than carried forward as a current value.

Not disclosedNot disclosed
29 Jul 2026announced 29 Jul 2026

FERC authorised the acquisition of Morgantown Power LLC (Docket EC26-58-000).

The first regulator-sourced record on the site, and a useful warning about headline approvals: FERC states the order covers the ownership transfer only. Data centre development, new generation, gas infrastructure, battery storage and any change to PJM participation each require separate review. Company guidance still contemplates data centre operations only in 2030.

Not disclosedNot disclosed

Upcoming catalysts

2
WULF

Anthropic / Justified — initial capacity delivery

First tranche of the approximately 401 MW Anthropic lease. Company guidance is H2 2027 — a half-year window, not a date. Would be the first energisation at the Justified campus.

WULF

Anthropic / Justified — full delivery

Completion of the approximately 401 MW lease. Guided to early 2028. Full delivery would take TeraWulf's contracted capacity toward acceptance and, contract terms permitting, revenue.

Make your call

Private to this browser

Write down what you expect TeraWulf to deliver, and by when. T2C scores it later against the same evidenced gates it uses everywhere else — not against the share price.

Stored in this browser only. Clearing your browser data deletes it, and T2C never receives it — there is nowhere for it to be sent.

About TeraWulf

Last verified 15 Aug 2026

TeraWulf develops powered data-centre campuses and leases them to compute tenants under long-term agreements, rather than owning the accelerators itself.

TeraWulf converts sites with strong power positions into data-centre capacity and leases that capacity to customers on long terms. Its Lake Mariner campus in New York is generating revenue, and a very large lease at its Justified campus does not begin delivering until the second half of 2027 — the gap between contracted and delivered is the central question for the company.

Company facts

Legal name
TeraWulf Inc.
Ticker / exchange
WULF · NASDAQ
Founded
2021
Headquarters
Easton, Maryland, United States
Business model
Powered shell
Last verified
15 Aug 2026

Who leads it

Paul B. Prager
Co-Founder, Chairman and Chief Executive Officer
In role since 1 Feb 2021

Co-founder of TeraWulf, serving as Chairman and Chief Executive Officer since February 2021. Previously founded and led Beowulf Electricity & Data.

↗ terawulf.comverified 15 Aug 2026

What it sells

  • Long-term data-centre leases to compute tenants
  • Powered campus development on owned and acquired sites
  • Power generation assets supporting those campuses

How it makes money

Leases powered, cooled space; the tenant supplies its own accelerators where the lease says so. Earns a few million per megawatt per year rather than tens, with correspondingly lower capital cost.

Where it operates

  • United States (New York, Maryland, Kentucky)

Operating presence as disclosed. This is not the same as future pipeline — a named location may hold nothing but secured power.

Publicly disclosed customers

  • Anthropic

Only customers the company has named publicly. Several tracked companies describe counterparties only as "investment-grade hyperscaler", and those are not guessed at here.

Official links

Social accounts are shown only where the link was found on a company-controlled domain. A verification badge alone is not treated as evidence.

Sources

3 documents