Polaris Forge 1

🇺🇸 United States · Applied Digital

Size
400 MW Critical IT
Customer
CoreWeave (Polaris Forge 1)
Status
The company has said it is being paid for capacity here.

400 MW leased to CoreWeave, approximately $11bn over a 15-year initial term. 250 MW live as of 1 October 2026.

News about this site

  • Loading the latest stories…

Key facts

  • 1 Oct 2026250 MW of the campus's 400 MW is fully operational: Building 1 (100 MW) and both 75 MW phases of Building 2, the second Ready for Service on 1 October 2026. Building 3 (150 MW) is under construction, with full ready for service guided for 2027.

On the record

  • 7 Oct 2026 Applied Digital adds 150 MW of energised critical IT↗ sec.gov