US data centre estate

🇺🇸 United States · CoreWeave

1.50 GW Critical IT
Not disclosed Customer
High Evidence confidence · 3 of 3 gates confirmed

CoreWeave reports fleet-wide rather than per site; the site-level split is not disclosed.

Path to billing

Furthest evidenced: Customer contracted
  1. Announced Not disclosed
  2. Power Not disclosed
  3. Build Not disclosed
  4. Accepted Not disclosed
  5. Billing Not disclosed

Each stage rolls up the project gates that evidence it. A stage marked Not disclosed has no gate on record — which is not the same as a stage the site has yet to reach.

Site view

Illustrative — not a photograph of this site

A generic campus illustration, shown to orient the layout of a site of this kind. It is not imagery of US data centre estate, carries no live telemetry, and no element of it is positioned from data. Every factual claim on this page is in the panels around it.

Latest evidence

Contracted power reached approximately 4.2 GW, up from 3.7 GW at quarter end.

11 Aug 2026

Dependencies

From tracked gates only
Power / grid Complete
Permits Not disclosed
Financing Not disclosed
Long-lead equipment Not disclosed
Customer Complete
Cooling Not disclosed
Networking Not disclosed

Site replay

Documented progression
Utility energised 30 Jun 2026
Critical IT energised 30 Jun 2026

Site status

  1. Announced
    Not disclosed
  2. Power secured
    Not disclosed
  3. Construction
    Not disclosed
  4. Energised
    Complete · 30 Jun 2026 · ↗ investors.coreweave.com
    1.5 GW active power.
  5. Customer contracted
    Disclosed in dollars of backlog, not megawatts.
  6. Acceptance
    Not disclosed
  7. Billing
    Not disclosed
Next

Acceptance

No date or window has been guided.

Customer contracts

No contract disclosure names this site. Where a company announces a customer without naming the location, the contract is held against the company rather than guessed onto a site.

What changed here

2 records
  • CRWV Advanced Confirmed US data centre estate

    Contracted power reached approximately 4.2 GW, up from 3.7 GW at quarter end.

    A further 500 MW of supply secured within six weeks of the quarter close. Contracted power is a total that already includes active capacity, so this widens the gap between power controlled and power energised rather than closing it.

    11 Aug 2026 3700 → 4200 MW
  • CRWV Advanced Confirmed US data centre estate

    Active power expanded by nearly 500 MW to reach 1.5 GW.

    The largest single-quarter energisation step on the board. The previous value is derived from the company's own "expanded by nearly 500 MWs" wording rather than a separately published Q1 figure.

    11 Aug 2026 1000 → 1500 MW