Panther Creek, Pennsylvania
🇺🇸 United States · Keel Infrastructure
- Size
- 350 MW Gross
- Customer
- Not named
- Status
- Announced, with no construction on record yet.
350 MW contracted firm power, of which 60 MW is currently energised. The 10-Q states that Panther Creek's energised capacity sits under NO energy service agreement and is therefore excluded from the company's own secured total — live power is not the same as secured power. The data centre itself is not evidenced as under construction.
News about this site
- Loading the latest stories…
Key facts
- 350 MW contracted firm power.
- "Secured zoning and land development approvals", with land development held conditionally.
- Environmental permit applications "progressing well"; the site is described as "nearing full permitting", which is not the same as permitted.
- No evidence the data centre itself is under construction.
On the record
- 11 Aug 2026 Keel Infrastructure passes a delivery milestone↗ sec.gov