Lake Mariner, New York
🇺🇸 United States · TeraWulf
102 MW revenue-generating critical IT plus 336 MW additional critical IT under construction across CB-4 and CB-5. CB-3 delivery completed in early July 2026.
Path to billing
- Announced Not disclosed
- Power Not disclosed
- Accepted Not disclosed
Each stage rolls up the project gates that evidence it. A stage marked Not disclosed has no gate on record — which is not the same as a stage the site has yet to reach.
Site view
A generic campus illustration, shown to orient the layout of a site of this kind. It is not imagery of Lake Mariner, New York, carries no live telemetry, and no element of it is positioned from data. Every factual claim on this page is in the panels around it.
Latest evidence
Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.
Dependencies
Site replay
Site status
-
Announced
-
Power secured
-
Construction
-
Energised
-
Customer contracted
-
Acceptance
-
Billing
Every tracked stage on this site is complete.
Customer contracts
No contract disclosure names this site. Where a company announces a customer without naming the location, the contract is held against the company rather than guessed onto a site.
What changed here
-
Lake Mariner reports 102 MW of revenue-generating critical IT, with 336 MW more under construction.
One of only two revenue-generating critical IT figures disclosed by any tracked company. The company's explicit "revenue-generating" wording is what allows this to be recorded as revenue-live.
11 Aug 2026 102 MW