Sites

Every project tracked at the level its milestones are actually evidenced — one record per site, with the gates it has passed and the documents that prove each one.

23 sites 18 disclose capacity 5 countries
23 shown
Infrastructure map Schematic � positions are not geographic

Schematic. The illustration is generic campus artwork and the pin positions are drawing coordinates — they are not geographic, and no tracked company publishes site coordinates. Tap a pin to open its site. Each pin opens the real site record behind it.

APLD

Delta Forge 1

🇺🇸 United States
300 MW

300 MW leased to a high investment-grade hyperscaler, approximately $7.5bn over a 15-year initial term.

Customer contracted
APLD

Delta Forge 2

🇺🇸 United States
210 MW

210 MW leased to a high investment-grade hyperscaler, approximately $5.2bn over a 15-year initial term.

Customer contracted
APLD

Polaris Forge 1

🇺🇸 United States
400 MW

400 MW leased to CoreWeave, approximately $11bn over a 15-year initial term.

Billing
APLD

Polaris Forge 2

🇺🇸 United States
200 MW

200 MW leased to an investment-grade hyperscaler, approximately $5bn over a 15-year initial term.

Customer contracted
APLD

Polaris Forge 3

🇺🇸 United States
300 MW

300 MW leased to a high investment-grade hyperscaler, approximately $7.5bn over a 15-year initial term.

Customer contracted
CRWV

US data centre estate

🇺🇸 United States
1.50 GW

CoreWeave reports fleet-wide rather than per site; the site-level split is not disclosed.

Customer contracted
IREN

British Columbia sites

🇨🇦 Canada
Not disclosed

Legacy capacity converting to GPU use.

Announced
IREN

Bundey, South Australia

🇦🇺 Australia
Not disclosed

Part of the 5 GW secured portfolio.

Announced
IREN

Childress, Texas

🇺🇸 United States
Not disclosed

Hosts the Microsoft Horizon tranches and the NVIDIA deployment.

Acceptance
IREN

Horizon 1 (Childress)

🇺🇸 United States
50 MW

Delivered to and accepted by Microsoft on 13 August 2026.

Acceptance
IREN

Horizons 2–4 (Childress)

🇺🇸 United States
150 MW

Remaining Microsoft tranches — the balance of the 200 MW contract after Horizon 1's 50 MW.

Customer contracted
IREN

Spain

🇪🇸 Spain
Not disclosed

Part of the 5 GW secured portfolio.

Announced
KEEL

Moses Lake, Washington

🇺🇸 United States
18 MW ~13 MW critical IT (est)

18 MW gross project capacity.

Energised
KEEL

Panther Creek, Pennsylvania

🇺🇸 United States
350 MW ~250 MW critical IT (est)

350 MW contracted firm power, of which 60 MW is currently energised.

Power secured
KEEL

Scrubgrass, Pennsylvania

🇺🇸 United States
1.30 GW

CORRECTION: previously shown as 1.3 GW of secured capacity.

Energised
KEEL

Sharon, Pennsylvania

🇺🇸 United States
110 MW ~79 MW critical IT (est)

110 MW gross total site capacity: 30 MW existing energised utility capacity plus 80 MW under an energy-services agreement with associated substation…

Power secured
KEEL

Sherbrooke, Québec

🇨🇦 Canada
96 MW

96 MW under a conditional transfer and operation agreement.

No stage evidenced
NBIS

Kansas City, Missouri

🇺🇸 United States
Not disclosed

US campus build-out.

Announced
NBIS

Mäntsälä, Finland

🇫🇮 Finland
310 MW

CORRECTION: 310 MW is the capacity this facility is expected to reach when fully deployed — planned project capacity, not capacity energised today.

Construction
WULF

Chesapeake (Maryland)

🇺🇸 United States
210 MW ~150 MW critical IT (est)

Approximately 210 MW operational generation at the Morgantown Generating Station.

Energised
WULF

Justified Data Campus (Anthropic)

🇺🇸 United States
401 MW

Approximately 401 MW critical IT on a 20-year initial lease, approximately $19bn contracted revenue over the initial term.

Customer contracted
WULF

Lake Mariner, New York

🇺🇸 United States
438 MW

102 MW revenue-generating critical IT plus 336 MW additional critical IT under construction across CB-4 and CB-5.

Billing
WULF

Muskie (Kentucky)

🇺🇸 United States
1 GW

Up to 1 GW of contracted electric service via Kentucky Power Company.

Power secured

Capacity figures state what they measure, and half this estate quotes gross power at the fence while the other half quotes critical IT in the hall. Where a site publishes only a gross figure, the comparable critical IT load is shown beneath it in amber as a T2C estimate — gross ÷ 1.4 — so the list can be read down one column. A site showing Not disclosed has published nothing to derive from: it is never shown as zero and never filled with a peer average. How estimates work.